Intermittent overnight single-lane and daytime shoulder closures on SR 169 are likely near Jones Lake through fall 2026 for ongoing fish passage construction. Flaggers will alternate traffic through the work zone during lane closures.
Project overview
This project will install five new concrete culverts along SR 169 in two locations in Black Diamond. These culverts will remove barriers to fish passage in Rock Creek, two tributaries to Jones Lake, Ginder Creek, and a tributary to Ginder Creek.
Construction began in August 2026 near Jones Lake. Crews installed 19- and 16-foot-wide concrete culverts along SR 169 that restored natural stream conditions along Rock Creek and a Jones Lake tributary where these waterways pass beneath the state highway.
During the 2027 construction season, crews will replace a second culvert that carries a tributary to Jones Lake beneath SR 169 north of SE 332nd Street. They also will install culverts beneath SR 169 at Black Diamond-Ravensdale Road and on Black Diamond-Ravensdale Road near SR 169. These culverts carry Ginder Creek and a tributary to Ginder Creek beneath SR 169.
Reconnecting waterways where our roads act as barriers is a priority for WSDOT. In western Washington, that means building hundreds of fish passable structures under state highways to create habitat essential for meeting fish recovery goals.
These new fish passage structures will greatly benefit the chum, coho, resident trout, steelhead and sea-run cutthroat that use these creeks. Replacing these culverts creates a combined potential habitat gain of 4.6 miles for native and migrating fish.
What to expect
2026 construction season
Contractor crews installed two fish-passable culverts that carry Rock Creek and an unnamed tributary to Jones Lake beneath SR 169. The work zone is located between Plass Road and SE 332nd Street near Jones Lake.
- SR 169 reopened on Sept. 17, 2026, following a 31-day road closure near Jones Lake.
- Intermittent overnight lane and shoulder closures along SR 169 are likely through the fall in this area.
- Construction will pause in late fall 2026 and then resume in spring 2027.
- Both directions of SR 169 will be open through the fall and winter near Jones Lake.
2027 construction season
In spring 2027, contractor crews will resume construction. Crews will likely start by replacing the third culvert carrying an unnamed tributary to Jones Lake beneath SR 169. The timeline for construction has not been finalized yet.
- Both directions of SR 169 will close between Jones Lake Road and South 332nd Street for about 25 days.
- Signed detours will guide people around the work zone, with separate routes for passenger vehicles and freight traffic.
- Local access will permitted, and homes and businesses in this area will remain accessible.
Crews also will work at the intersection of SR 169 and Black Diamond-Ravensdale Road. There, they will replace a culvert that carries Ginder Creek and a tributary to Ginder Creek beneath SR 169.
- Both directions of SR 169 will close near the intersection with Black Diamond-Ravensdale Road for up to 60 days.
- Full or partial road closures are possible along Black Diamond-Ravensdale Road near the intersection with SR 169.
- Signed detours will guide people around the closures.
- Homes and businesses in this area will remain open and accessible.
- Construction will continue into fall 2027 then pause until spring 2028.
- Both directions of SR 169 will be open through the late fall 2027 and spring 2028 near Black Diamond-Ravensdale Road.
2028 construction season
Crews will resume construction in spring 2028. They will work to complete any remaining work at both project locations, complete final paving and lane striping as needed and work to finish the project in October 2028. This schedule depends on favorable weather during the 2026 and 2027 construction seasons and could change.
A map showing the location of five culverts that cross beneath SR 169 in Black Diamond that will be replaced starting in mid-2026.
To protect and restore fish runs, WSDOT is correcting fish barriers found under state highways. Since 1991, when WSDOT created a dedicated program, 365 barriers have been corrected, opening a total of 1,215 miles of fish habitat.
We will replace existing culverts with new fish passable structures. Opening habitat allows more salmon and steelhead at all life stages, including juveniles that aren’t yet strong swimmers like adults, to access important spawning and rearing habitat, including areas that haven’t been accessed in years.
Improvements to fish passage also benefits commercial seafood operations, recreational fishers, and provides more food for our declining orca population. In addition, replacing these culverts helps us meeting our obligation to remove barriers under a 2013 U.S. District Court injunction.