Project overview
We rehabilitated more than 3 miles of pavement, replacing broken panels and grinding the surface to eliminate ruts worn by decades of vehicles. In addition, we replaced expansion joints on four bridges. This project was combined with another rehabilitation project on I-90 to reduce costs.
Timeline
Fall 2022 - Fall 2023
Project status
Completed
Funding
$7.9 million
What to expect
Work is complete.