US 195 – Cornwall Road to Cheney-Spokane Road – NB Lanes Only – Paving

Project overview

This project will rehabilitate roughly 11 miles of northbound US 195 from Cornwall Road to Cheney-Spokane Road in Spokane County. This project will grind and inlay new HMA (Hot Mix Asphalt), the roadway surface will have a smoother ride that will be preserved for years to come.

Timeline
August 2024 - Summer 2025
Project status
Construction
Funding
$7.2 Million
Project hotline

What to expect

This project is 45 working days and is scheduled to begin Monday, August 12. Travelers can anticipate some delay with single-lane, shoulder and median closures between 9:30 a.m. and 8:30 p.m. Monday through Thursday and Saturday's.

Approaches and median crossovers at Hatch, Excelsior, and Paradise Roads will not be closed between 7 a.m. and 9 a.m. and 3 p.m. and 6 p.m. The Cheney-Spokane interchange exit ramp will have a signed detour when it is closed. 

Map location for the US 195 northbound lanes paving project between Cornwall Road and Cheney-Spokane Road.