• Project

US 101/Delphi Rd to I-5 - Paving and Concrete Barrier - Complete October 2022

Project overview

Workers repaired the surface of southbound US 101 in areas between Mud Bay and US 101 in Tumwater. Crews also made safety improvements on the southbound US 101 ramp to northbound I-5 in Tumwater

Timeline
May 2022 - October 2022
Project status
Completed
Funding
$2.6 million

What to expect

Contractor crews replaced asphalt on the left lane of southbound US 101 between Mud Bay Road and Crosby Boulevard. Crews also installed fresh asphalt in the right lane of US 101 between Black Lake Boulevard and the on-ramp to southbound I-5. Three highway ramps also were paved. Crews also installed new barrier on the southbound US 101 on-ramp to northbound I-5 in Tumwater.