• Project

SR 522 - I-5 to 61st Ave NE - Paving & ADA Compliance

Project overview

WSDOT contractor crews will repave sections of SR 522, commonly known as Lake City Way or Northeast Bothell Way, which were last paved in 2002.

Timeline
Spring 2020 to Fall 2021
Project status
Construction
Funding
$15 Million

What to expect

Wednesday, Sept. 15 until further notice: expect a lane shift on each direction of SR 522/Lake City Way at NE 95th Street in Seattle. Crews will continue construction on a retaining wall along the roadway. 

In addition to repaving sections of SR 522, WSDOT is working with the Seattle Department of Transportation to make pedestrian improvements at four locations along the highway, including new crosswalks and crossing signals, new sidewalks and improved curb ramps to provide better sidewalk connections for people of all abilities.