• Project

I-90/142nd Pl SE over I-90 - Bridge repair

Project overview

Starting March 6, 2023, contractor crews will repair a girder that supports 142nd Place Southeast over Southeast Eastgate Way and I-90. The girder was damaged when it was struck by a truck hauling construction equipment that was too tall. The northbound lane of 142nd Place Southeast remains closed. Work will be complete by mid April.

Timeline
Winter 2023
Project status
Construction
Funding
$600,000

What to expect

Southeast Eastgate Way is closed to all vehicles 24 hours per day near the 142nd Place overpass. People who use the 148th Avenue Southeast on-ramp to westbound I-90 also should expect closures. People can still get to all businesses along Eastgate Way. This closure will last until early April.

Crews will need to close Southeast Eastgate Way near the Eastgate Park and Ride for about five weeks to repair a damaged steel girder that supports the 142nd Place Southeast overpass.