• Project

I-5/Southbound 100th Street Southeast Vicinity to Broadway Avenue – Paving

Project overview

This project will grind and pave about four miles of southbound Interstate 5 in Everett, from 100th Street Southeast to Broadway Avenue. Crews working for WSDOT will pave the mainline. This project will also replace impacted traffic loops, pavement markings and replace bridge joints.

Timeline
Spring 2025 – Fall 2025
Project status
Pre-construction
Funding
$8.1 million

What to expect

Contractor crews are scheduled to begin work in summer 2025. Travelers can expect shoulder, ramp and up to four-lane closures in this six-lane section of I-5. For ramp closures, traffic will be detoured to the next southbound I-5 exit. Daytime and nighttime work is expected. Work is not currently scheduled.

This project will rehabilitate about four miles of southbound I-5 in Everett, from 100th Street Southeast to Broadway Avenue.