Project overview

During fall 2022, contractor crews replaced the damaged girder on the 12th Street Bridge over Interstate 5 between Everett and Marysville. In addition to replacing the girder, part of the bridge deck and barrier were rebuilt.

Timeline
August 2022-winter 2023
Project status
Completed
Funding
$1.8 million

What to expect

Work on this project is complete. Contractor crews replaced the damaged girder for the 12th Street overpass the weekend of Dec. 10-11, then rebuilt part of the bridge deck.

Work on northbound I-5, which require some overnight detours to Marine View Drive, is complete.