• Project

SR 112 - W of Jim Creek Landslides - Emergency Repairs - Complete July 2021

Project overview

This project repaired an unstable slope along State Route 112 in Clallam County. Crews reopened the highway to two-way travel on Friday, July 9, 2021.

Timeline
Dec. 2020 - July 2021
Project status
Completed
Funding
$1.4 Million

What to expect

No additional lane or highway closures are anticipated related to this work. 

During Dec. 2020, State Route 112 settled due to a chronic unstable slope. Some areas dropped as much as 13 feet.