Pre-existing Funds

2023 Q4 (Q2 2023-2025 biennium)

WSDOT advertises nine Pre-existing Funds projects in the second quarter of the biennium

WSDOT advertised nine PEF projects during the quarter ending December 31, 2023. WSDOT's current cost to complete the 49 actual PEF projects advertised through the second quarter of the 2023-2025 biennium was about $906.5 million, approximately $77.7 million (9.4%) more than the original value of $828.8 million.

2023 Q3 (Q1 2023-2025 biennium)

WSDOT advertises 40 Pre-existing Funds projects in the first quarter of the biennium

As of September 30, 2023, WSDOT's current cost to complete the 40 actual PEF projects advertised through the first quarter of the 2023-2025 biennium was about $581.5 million, approximately $53.1 million (10.0%) more than the original value of $528.4 million.

2023 Q2 (Q8 2021-2023 biennium)

WSDOT advertises 43 Pre-existing Funds projects in the eighth quarter of the biennium

As of June 30, 2023, WSDOT's current cost to complete the 388 actual PEF projects advertised through the eighth quarter of the 2021-2023 biennium was about $3.0 billion, approximately $1.5 billion (94.9%) more than the original value of $1.5 billion.

WSDOT had 100 emergent and 47 emergency projects during the biennium. In response to the Governor's COVID-19 stay at home order, WSDOT directed a temporary construction suspension on most projects throughout the state. In addition, the project costs were further increased due to significant inflation factors. Delays in right of way acquisition increased right of way acquisition costs.

2023 Q1 (Q7 2021-2023 biennium)

WSDOT advertises 52 Pre-existing Funds projects in the sixth quarter of the biennium

As of March 31, 2023, WSDOT's current cost to complete the 345 PEF projects advertised through the seventh quarter of the 2021-2023 biennium was about $2.4 billion, approximately $1.1 billion (82.5%) more than the original value of $1.3 billion.

2022 Q4 (Q6 2021-2023 biennium)

WSDOT advertises 46 Pre-existing Funds projects in the sixth quarter of the biennium

As of December 31, 2022, WSDOT's current cost to complete the 293 PEF projects advertised through the sixth quarter of the 2021-2023 biennium was about $1.54 billion, approximately $607.3 million (64.9%) more than the original value of $935.6 million.

2022 Q3 (Q5 2021-2023 biennium)

WSDOT advertises 36 Pre-existing Funds projects in the fifth quarter of the biennium

As of September 30, 2022, WSDOT's current cost to complete the 247 PEF projects advertised through the fifth quarter of the 2021-2023 biennium was about $1.25 billion, approximately $455.0 million (56.7%) more than the original value of $801.9 million.

2022 Q2 (Q4 2021-2023 biennium)

WSDOT advertises 74 Pre-existing Funds projects in the fourth quarter of the biennium

As of June 30, 2022, WSDOT's current cost to complete the 191 PEF projects advertised through the fourth quarter of the 2021-2023 biennium was about $840.4 million, approximately $233.7 million (38.5%) more than the original value of $606.7 million.

2022 Q1 (Q3 2021-2023 biennium)

WSDOT advertises 58 Pre-existing Funds projects in the third quarter of the biennium

As of March 31, 2022, WSDOT's current cost to complete the 117 PEF projects advertised through the third quarter of the 2021-2023 biennium was about $573.2 million, approximately $126.1 million (22.0%) more than the original value of $447.1 million.

2021 Q4 (Q2 2021-2023 biennium)

WSDOT advertises 51 Pre-existing Funds projects in the second quarter of the biennium

As of December 31, 2021, WSDOT's current cost to complete the 79 PEF projects advertised through the second quarter of the 2021-2023 biennium was about $420.2 million, approximately $114.6 million (37.5%) more than the original value of $305.6 million.

2021 Q3 (Q1 2021-2023 biennium)

WSDOT advertises 28 Pre-existing Funds projects in the first quarter of the biennium

As of September 30, 2021, WSDOT's current cost to complete the 28 PEF projects advertised through the first quarter of the 2021-2023 biennium was about $86.7 million, approximately $400,000 (0.5%) more than the original value of $86.3 million.

2021 Q2 (Q8 2019-2021 biennium)

WSDOT advertises 41 Pre-existing Funds projects in the eighth quarter of the biennium

As of June 30, 2021, WSDOT's current cost to complete the 278 PEF projects advertised through the eighth quarter of the 2019-2021 biennium was about $964.3 million, approximately $216.6 million (29.0%) more than the original value of $747.7 million. This difference was primarily due to the large number of emergent projects during the biennium.

2021 Q1 (Q7 2019-2021 biennium)

WSDOT advertises 38 Pre-existing Funds projects in the seventh quarter of the biennium

As of March 31, 2021, WSDOT's current cost to complete the 237 PEF projects advertised through the seventh quarter of the 2019-2021 biennium was about $764.4 million, approximately $105.2 million (16.0%) more than the original value of $659.2 million.

2020 Q4 (Q6 2019-2021 biennium)

WSDOT advertises 45 Pre-existing Funds projects in the sixth quarter of the biennium

As of December 31, 2020, WSDOT's current cost to complete the 219 PEF projects advertised through the sixth quarter of the 2019-2021 biennium was about $722.2 million, approximately $132.2 million (22.4%) more than the original value of $590.0 million

2020 Q3 (Q5 2019-2021 biennium)

WSDOT advertises 20 Pre-existing Funds projects in the fifth quarter of the biennium

As of September 30, 2020, WSDOT's current cost to complete the 154 planned PEF projects advertised through the fourth quarter of the 2019-2021 biennium was about $376.2 million, approximately $25.4 million (7.8%) more than the original value of $350.8 million.

2020 Q2 (Q4 2019-2021 biennium)

WSDOT advertises 20 Pre-existing Funds projects in the fourth quarter of the biennium

As of June 30, 2020, WSDOT's current cost to complete the 134 planned PEF projects advertised through the fourth quarter of the 2019-2021 biennium was about $344.3 million, approximately $9.7 million (2.9%) more than the original value of $334.6 million.

2020 Q1 (Q3 2019-2021 biennium)

WSDOT advertises 52 Pre-existing Funds projects in the third quarter of the biennium

At the beginning of the 2019-2021 biennium, WSDOT's current cost to complete the 115 planned PEF projects advertised during the quarter was about $308.3 million, approximately $10.3 million (3.5%) more than the original value of $298.0 million.

2019 Q4 (Q2 2019-2021 biennium)

WSDOT advertises 39 Pre-existing Funds projects in the second quarter of the biennium

At the beginning of the 2019-2021 biennium, WSDOT's current cost to complete the 63 planned PEF projects advertised during the quarter was about $159.3 million, approximately $6.3 million (4.1%) more than the original value of $153.0 million.

2019 Q3 (Q1 2019-2021 biennium)

WSDOT advertises 24 Pre-existing Funds projects so far during the 2019-2021 biennium

At the beginning of the 2019-2021 biennium, WSDOT's current cost to complete the 24 planned PEF projects advertised during the quarter was about $32.0 million, approximately $200,000 (6.0%) less than the original value of $32.2 million.

2019 Q2 (Q8 2017-2019 biennium)

WSDOT advertises 459 Pre-existing Funds projects during the 2017-2019 biennium

At the close of the 2017-2019 biennium (July 2017 through June 2019), WSDOT's current cost to complete the 459 PEF projects advertised was about $1.03 billion, approximately $93.5 million (9.9%) more than the original value of $941.1 million.

2019 Q1 (Q7 2017-2019 biennium)

WSDOT advertises 417 Pre-existing Funds projects so far during the 2017-2019 biennium

To date in the 2017-2019 biennium (July 2017 through June 2019), WSDOT's current cost to complete all 417 PEF projects that have been advertised is $934.4 million, about $49.1 million (5.5%) more than the original value of $885.3 million.

Pre-existing Funds projects



Top of page