SCHEDULE

Revised 09/27/16

The Expert Review Panel met six times between May 2015 and June 2016. The meetings and topics covered were as follows:


MAY 4-5, 2015
Orientation
Progress of ST2
Long-Range Plan, Environmental Impact Statement
2015 System Planning Efforts

JULY 13-14, 2015
Methodologies: capital cost, operations & maintenance cost, ridership forecasting, evaluation

NOVEMBER 9-10, 2015
System Plan Requirements
Board Direction on Priority Project List
Financial Planning Assumptions
Continued Review of Methodologies
Follow-up from July Meeting

FEBRUARY 8-9,2016
Review Evaluation of Draft System Plan
Review ST3 Finance Plan and Financial Planning Assumptions
Discussion of Review of ST3 Project Cost Estimates
Discussion of Review of ST3 Project Ridership Estimates

April 11 - 12, 2016
Review March 2016 Draft System Plan
Planning and environmental process
Plans for public outreach

JUNE 6, 2016

Review ST3 Finance Plan
Discussion of Draft System Plan Update
Review public outreach response to date


The exact meeting dates will be added to this page as they are set.