Submitted by webhelp on Fri, 12/30/2016 - 18:10
Project news
US 395 was resurfaced with hot mix asphalt. ADA sidewalk work was included. Some minor corrective items remain. Central Washington Asphalt of Moses Lake, WA handled the project with a construction bid of $3,491,873.
Needs & benefits
High traffic volumes with normal wear and tear had deteriorated the pavement surface. Resurfacing provides a better experience for drivers with a reduced need for repairs and patching.
Submitted by webhelp on Fri, 12/30/2016 - 18:08
Project news
SR 290, Trent Avenue was resurfaced from the Mission Ave. "Y" to Sullivan road. In addition, the bridge decks on the Spokane River Bridges near Pines Road were repaired and the eastbound SR 290/UPRR bridge deck was repaired.
Needs & benefits
Economic Incentive
A smoother roadway and protection for the underlying highway structure makes a better experience for drivers with a reduced need for expensive repairs and patching.
Partnerships and cooperation
Submitted by webhelp on Fri, 12/30/2016 - 18:06
Project news
Overview
SR 270 was resurfaced with Hot Mix Asphalt. This included Davis Way, a short section of Grand Ave., Main Street, and Paradise Street. Sidewalk curb ramps were constructed to federal ADA standards.
Needs & benefits
Economic Incentive
Repairing the pavement created a smoother drive and protects the public investment in the roadway.
Improves Safety
Sidewalk curb ramps were built to current ADA slope standards.
Submitted by webhelp on Fri, 12/30/2016 - 18:01
Submitted by webhelp on Fri, 12/30/2016 - 17:54
In 2014-2015, Corridor Review Study was performed with extensive community input to explore traffic movement opportunities in this area. The study identified affordable near-term safety improvements on US 2 from Deer Road to Day Mt. Spokane Road that are part of this 2017 construction project.
Submitted by webhelp on Fri, 12/30/2016 - 17:52
Overview
US 2/Division Street north of Francis Avenue was resurfaced new layer of hot mix asphalt will preserve the underlying roadway structure and provide a smooth driving surface. The work was handled by CPM/Inland Asphalt Company of Spokane with a construction bid of $1,777,500.
Needs & benefits
Economic Incentive
This project protects the public investment in the infrastructure.
Partnerships and Cooperation
WSDOT engineers worked closely with adjacent businesses to minimize project affects.
Submitted by webhelp on Fri, 12/30/2016 - 17:49
Project news
- Awarded to the Max J. Kuney Company of Spokane with a construction bid of $7,655,561.
Needs & benefits
Submitted by webhelp on Fri, 05/20/2016 - 17:02
Project News
Construction on the East Trent Bridge began Monday, March 9, 2020. The full closure for demolition and reconstruction of the East Trent Bridge began on June 1, 2020.
Several detours will go into place during construction.
Submitted by webhelp on Thu, 01/07/2016 - 00:17
Project news
- Most work complete. Minor items remain.
In this project, ADA improvements were made at selected intersections on US 2 and SR 290 in the Spokane area, SR 902 in Medical Lake, SR 904 in Cheney and the Sprague Lake rest areas. The selected intersections had the ADA features brought up to current standards. The work was handled by the Wm. Winkler Company of Newman Lake, WA with a construction bid of $1,093,778.
Project Benefits
Improves Safety
Improved access for citizens.
Submitted by webhelp on Tue, 01/05/2016 - 20:13
Project news
February 2019
- WSDOT is working on a preferred solution to construct a new single bridge. This will replace the current two structures. The project will be programmed for construction in 2025.
Winter 2017
Submitted by webhelp on Tue, 01/05/2016 - 19:55
Project news
- This project was awarded to Specialized Pavement Marking, Inc. of Tulation, OR with a construction bid of $1,526,969.
This project includes installation of enhanced striping and signage at selected intersections on US 2 and US 395.
Why is WSDOT addressing these intersections?
Enhanced signage and striping may assist drivers as they approach intersections of local roads with high-speed highways.
The End Result
Higher visibility for busy intersections to assist drivers.
Submitted by webhelp on Thu, 12/31/2015 - 16:35
What to expect
Crews will be closing the eastbound I-90 on-ramp starting Sunday, Oct. 11, at 6 p.m. until Thursday, Oct. 15, at 5 a.m. Crews will be reconstructing the on-ramp to connect with the new roundabout. Drivers will detour to the Geiger/Grove Rd. interchange via Aero Road to Westbow Road, Thomas Mallen Road, and Grove Road during the closure.
The SR 902 Interchange Reconstruction project is located at the existing Highway 902 Interchange at exit 272 along I-90. The project includes the construction of -
Submitted by webhelp on Tue, 02/11/2014 - 20:22
Project news
Winter 2017
Needs & benefits
Why is WSDOT conducting a US 2 / Deer Road to Elk-Chattaroy Corridor Study?
Submitted by webhelp on Tue, 07/05/2005 - 16:07
Project news
2020 North Spokane Corridor Projects
Submitted by webhelp on Thu, 09/16/2004 - 21:52