US 395 - North Spokane Corridor - Construction staging

Timeline of remaining North Spokane Corridor construction:

  1. Under construction: Columbia to Freya - Completed August 2020
  2. BNSF 2nd Railroad Realignment - Construction began September 2019
  3. Spokane River to Columbia - Construction started May 2021
  4. Wellesley Ave. Improvements - Construction starts summer 2021
  5. Children of the Sun Trail - Construction starts summer 2021
  6. Sprague Ave. to Spokane River Phase 1 - Construction starts June 2021
  7. Spokane River Crossing - Construction starts 2022
  8. Sprague Ave. to Spokane River Phase 2 - Construction starts 2023
  9. I-90 to Sprague Ave. - Construction starts 2023

North Spokane Corridor construction staging map to completion from Francis Ave. down to I-90/

Construction staging of the North Spokane Corridor to I-90.