US 2 - Eagle Falls Vic to Tye Creek - Bridge Decks Overlay

Project news

  • Monday, July 26, to the evening of Thursday, July 30 - Travelers on US 2 between Gold Bar and Index should expect daytime alternating traffic Monday through Thursday evening.
  • This contract was awarded in Jan. 2020 to Max J. Kuney Company of Spokane, WA.
  • Sign up to receive email updates about this project and other Snohomish County topics.

Overview

In July 2021, contractor crews with Max J. Kuney company will complete repairs to the bridge decks on nearly two dozen structures along US 2 between the area west of Index (Proctor Creek/Big Bend) and Skykomish (Tye River vicinity).

Needs & benefits

Nineteen bridges on this 23 mile stretch of US 2 are in need of repairs. The pavement on the bridges dates back to 2002 and has outlived its anticipated 15 year lifespan. This preservation work requires removing the old asphalt, inspecting the bridge deck and making any necessary repairs then putting down waterproof material. This material protects the steel rebar from rusting. Crews will also repair any damaged expansion joints then put down the new asphalt surface.

Properly rehabilitating these bridges also reduces the need for emergency repairs which can be costly to taxpayers and cause additional congestion if the work must be done during peak commute hours.

What travelers should expect

Most of the work will happen during single lane closures with alternating one-way traffic. Traffic holds may last up to 20 minutes. Several of the bridges are very narrow at just 24 feet wide and no shoulder. During lane closures, the open lane of travel may be just 10 or 11 feet wide. To protect workers and travelers in these narrow work zones, the speed limit may be reduced from 55 or 60 miles per hour to 10 miles per hour.

Timeline

  • November 2019: Advertised for competitive bidding.
  • Jan. 2020: Contract awarded to Max J. Kuney Company of Spokane, WA.
  • spring 2020: Construction scheduled to begin.
  • summer 2021: Construction scheduled to be complete.

Funding

This project is estimated to cost $4.66 million with funding from federal and state sources.

Financial Information

Financial Data for PIN 100251C, 100256A, 100261B
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $3,280
CWA $1,125
Total $4,404

Contact

Joseph Calabro
WSDOT Communications
206-440-4452
Joseph.Calabro@wsdot.wa.gov

General project location of 2020 bridge deck rehabilitation work on US 2 in Snohomish County.