Awarded to N.A. Degerstrom, Inc. of Spokane Valley, WA with a construction bid of $1,426,551.
Repair erosion damage and re-establish the slope adjacent to the bridge.
All project work was physically complete on Oct. 2, 2018.
Connecting Washington/Federal STP/State MVA = $2,036,871
Tom Brasch, project engineer