I-90 - SR 21 to Ritzville - Paving

Project news

Project is complete. Minor cleanup items remain. Seeding of the pit and project area on hold until the seeding window on October 1.

Needs & benefits

This project will restore 9.9 miles of the existing asphalt pavement by grinding and placing 0.15 foot depth of asphalt on the driving lanes and shoulders. The project will extend between the Lind and Ritzville interchanges.

Timeline

Construction began on April 15. All contract work was completed the week of June 10. Minor items remain.

View current construction and traffic impacts.

Funding

Financial Data for PIN 609020I
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $8,036
CWA $0
Total $8,036

Contact

Tom Brasch, project engineer
2714 N. Mayfair St.
Spokane, WA 99207
(509) 323-8411

Location of paving from SR 21 to Ritzville