2021 Chip Seal - Complete July 2021

Project news

The contract was awarded to Central Washington Asphalt, Inc. 

Needs & benefits

The Eastern Region 2021 Chip Seal includes two sections of roadway:

  • SR 26 - Laurel Road to Washtucna
  • SR 274 from the junction with SR 27 to the Idaho State Line. 

Both sections will be crack sealed, have pavement repair, preleveling, bituminous surface treatment, fog sealing, pavement markings, and guidepost replacements. Traffic control may include lane closures, flaggers, and pilot cars.

Timeline

Construction was completed in early July.

Funding

Financial Data for PIN's 602606K and 627400U
Amount ($ in thousands)

  • PEF (Pre-Existing Funds) - $2,411
  • Total - $2,411