PGSplice 7.0
Precast-prestressed Spliced Girder Bridges
|
| Item | Description |
|---|---|
| Day when this event occurs | Enter the start day of this event |
| Event Description | Enter a name that describes the construction activities that take place during this event. |
| Event Activities | Grid listing the construction activities that occur during this event. Press [Edit] to edit the details of an activity. |
| [Add] | Press and select an activity from the drop down menu to add an activity to this event |
| [Remove] | Select an activity in the Event Activities grid and press to remove the activity from this event. |
NOTE: The elapsed time of an event is taken to be the duration of its longest activity.
TIP: A time-step event is an event without any activities. Time-step events are useful for refining the time-step analysis.
See Construction Sequence in the User Guide for more details about modeling the construction sequence timeline.