PGSplice
3.0
Precast-prestressed Spliced Girder Bridges
|
Define general information about the span.
Item | Description |
---|---|
Span Length | Enter the span length measured along the alignment between the abutment/pier lines at either end of the span. |
The length of the span is changed by moving all the up-station piers.
Define the slab offset for the span.
Item | Description |
---|---|
Type | Click on the combo box to select if the slab offset is for the entire bridge or only for this span. |
Start | Slab offset at the start of the span |
End | Slab offset at the end of the span |