Select the segments that are erected during this event.
Item | Description |
---|---|
Segments to be erected | List of all the segments. Segments with black text have not been assigned to an event. Segments with gray text are assigned to a different event and can be moved into this event. |
Segments erected during this activity | List of the segments that are erected during this activity. |
[>] and [<] | Move segments between the two lists |