PGSuper offers several methods of defining girder spacing. This section will detail the methods of defining girder spacing and their implications on the bridge geometry.

To properly position the girders in the bridge, PGSuper needs to know the spacing between girders and the transverse location of the girders.

Girder Spacing

Girder spacing can be measured at the Abutment/Pier Line or at the CL Bearing. At these locations the girder spacing is measured either normal to the alignment or along the specified line. The methods for defining the girder spacing are:

  • Measured at and along the Abutment/Pier Line
  • Measured normal to the alignment at the Abutment/Pier Line
  • Measured at and along the centerline bearing
  • Measured normal to the alignment at the centerline bearing

Transverse Location of Girders

The girders must be located transversely as well. The transverse location is described by an offset from either the Bridge Line or the Alignment. This offset is measured in the same direction as the girder spacing. The offset can be measured to a specific girder or to the center of the girder spacing.

Girder Spacing Examples

The following examples illustrate how girder spacing is defined.

Here the girder spacing is measured along the CL Pier/CL Bearing. The girders are located transversely by defining the offset from the alignment to the left exterior girder.

girder_spacing_on_pier.gif

Here the girder spacing is measured Normal to the alignment at the CL Pier/CL Bearing. The girders are located transversely by defining the offset from the alignment to the left exterior girder.

girder_spacing_on_normal.gif

Transverse location of girders by defining location of a specific girder

transverse_location1.gif

Transverse location of girders by defining the location of the center of girders