Healthy Environment for All Act
The SR 3 Craig to Arcadia project is a Significant Agency Action. Under the HEAL Act, WSDOT is required to prepare an environmental justice assessment. During the pre-design, WSDOT identified vulnerable populations and overburdened communities that may be impacted by the project. WSDOT used this information to conduct community engagement and prioritize recommended improvements.
Target Zero is WSDOT’s safety improvement program. It aims to reduce serious and fatal crashes on state highways. The program focuses on two aspects: crash reduction and crash prevention.
Complete Streets are streets designed for everyone. WSDOT uses Complete Streets to create safer and more accessible roadways for all users. To do this, Complete Streets looks at several elements. This includes:
Studies show that roundabouts are safer than traffic signals or stop signs. They accommodate vehicles of various sizes, including:
- Emergency vehicles
- Buses
- Bicycles
- Semi-trucks with trailers
- Farm and logging equipment
Community engagement summary
The pre-design team held pop-up events at OysterFest and a community resource fair. WSDOT staff provided information about the project and listened to community concerns.
An online open house was live from March 23 to April 7, 2026. The online open house content was in English and Spanish. More than 2,200 people visited the online open house, and 129 people responded to the survey.
Survey results
Respondents to the online open house were asked to rank their preference for different types of bike lane separation. WSDOT will evaluate the feasibility of different bike lane designs during the design phase. Sidewalk level bike lanes were the highest ranked option by the respondents. Tubular markers ranked the lowest.
WSDOT received 129 comments on the online open house. Below are responses to some common themes we heard.
- Why is WSDOT recommending a roundabout at Mill Creek Road?
Many commenters asked why WSDOT is recommending a roundabout at Mill Creek Road. A roundabout in this location is needed to allow for the median along SR 3. This location allows drivers to make U-turns, and for residents along Mill Creek Road to turn left onto SR 3. The median and roundabouts work together to reduce the risk of a serious or fatal crash. These improvements encourage drivers to travel the speed limit as they enter Shelton.
- Why is WSDOT doing Complete Streets?
Complete Streets is a comprehensive approach to planning, designing, building, operating, and maintaining our roads. At WSDOT, it refers to the requirement signed into law in 2022 and codified in RCW 47.04.035 to address gaps in the walking and bicycling networks in communities when we are doing state transportation projects. WSDOT looks at new Complete Streets facilities in population centers. On this project, that is the more developed areas of SR 3, north of East Delanty Road.
- Nearby WSDOT Projects
Many commenters asked about other WSDOT projects near Shelton. Below is information on several ongoing Projects:
SR 3 Agate and Pickering roundabouts
WSDOT is building two roundabouts on SR 3 at Agate Road, and Pickering Road north of Shelton. These roundabouts are in the design phase.
SR 3 Freight Corridor
WSDOT is designing a new route for SR 3 while maintaining the existing highway through Belfair as a bypass of the main highway. This project is currently in the design phase.
SR 3 Mason Lake Road Roundabout
WSDOT is planning to build a roundabout at the intersection of SR 3 and Mason Lake Road north of Shelton. The project is currently in the design phase.
SR 3 Division Avenue Roundabout
WSDOT is planning to build a roundabout at the intersection of SR 3 and Division Avenue, and Complete Streets improvements near West Pleasant Street. The project is currently in the design phase.
SR 3 Gorst Area Planning and Environmental Linkages Study
WSDOT began a Planning and Environmental Linkages study to look at SR 3, 16, 166 and 304 in the Gorst area. This study evaluates a range of alternatives that improve transportation for all roadway users. The study team is finishing alternatives screening and drafting the PEL report.
- How will roundabouts accommodate trucks and large vehicles?
Several people asked how trucks and large vehicles will drive through roundabouts. WSDOT designs roundabouts to accommodate vehicles of all sizes. This includes emergency vehicles, buses, farm equipment, and semi-trucks with trailers.
- Recommended Median
Several commenters asked how the median will impact emergency vehicles. WSDOT will look at different materials for the median during the design phase. This includes mountable curbing, and paint. The median material could vary throughout the project limits. Changing the material can improve access for emergency vehicles and WSDOT maintenance crews.
- Traffic Modeling
WSDOT used Signalized and unsignalized Intersection Design and Research Aid, also known as SIDRA. It is traffic modeling software. The pre-design team used SIDRA to forecast traffic patterns the roundabouts. WSDOT used the traffic growth rate from the Shelton and the Mason County Comprehensive Plans. The modeling results were within WSDOT standards.
- Property Acquisition
Some people asked about the potential acquisition of private property for this project. WSDOT has not yet determined the right of way acquisition needs. WSDOT still needs to collect survey data and complete roundabout designs. WSDOT will decide the property needs of the project during the design phase.
Next steps
WSDOT has concluded the pre-design phase. The project will now move into design. During design, engineers will refine the pre-design concepts. After the design phase the project will begin construction.