Search projects

Learn about current transportation network improvement and preservation activities throughout the state.

You might be looking for studies or local agency managed projects

Filter projects

Select
Select
Select
Select

224 results

Project

SR 112 - W of Jim Creek Landslides - Emergency Repairs - Complete July 2021

Timeline: Dec. 2020 - July 2021
  • Rail
  • Completed
  • Clallam County
This project repaired an unstable slope along State Route 112 in Clallam County. Crews reopened the highway to two-way travel on Friday, July 9, 2021.
Project

SR 112/Clallam Bay - Emergency Repairs - Complete July 2022

Timeline: Nov. 2021 - July 2022
  • Road
  • Completed
  • Clallam County
Crews reopened State Route 112 near Clallam Bay to two-way travel at 6 p.m. Monday, March 21. The highway closed on Monday, Nov. 15, 2021 due to massive landslide and regionwide flooding. The detour using Eagle Crest Way has been removed.

Crews worked to remove additional slide…
Project

SR 112/Jim Creek West - Emergency Repairs - Complete June 2022

Timeline: Nov. 2021 - Summer 2022
  • Road
  • Completed
  • Clallam County
Construction to reopen State Route 112 at milepost 32 began Monday, March 28, 2022 after the highway dropped almost 4-feet. Work at Jim Creek includes: slope stabilization efforts, roadway repairs, installation of new guardrail, installation of new trench and horizontal drains, replacement of three…
Project

SR 112/W Rasmussen Creek and Hoko River – Emergency Project

Timeline: Summer - Fall 2022
  • Road
  • Construction
  • Clallam County
This emergency project will take place at two sites on SR 112 in Seiku: at milepost 4.6 near Rasmussen Creek and at milepost 11.4 on the Hoko River.

At Rasmussen creek, construction crews will rebuild and replace two areas of the embankment, which slid into the Strait of Juan de Fuca…
Project

SR 113/S of Old Sappho-Pysht Hwy – Stabilize Slope - Completed August 2022

Timeline: Nov. 2021 - August 2022
  • Road
  • Completed
  • Clallam County
This project will repair an unstable slope and replace a clogged culvert under Burnt Mountain Road (SR 113) near Beaver in Clallam County. A new culvert and stabilized hillside will allow water to flow properly through the area without the use of a temporary water pump, preventing additional…
Project

SR 14 - 0.7 to 0.2 Miles W. of Chamberlain Lake Rest Area - Unstable Slope

Timeline: Nov. 2021 - June 2022
  • Road
  • Construction
  • Klickitat County
Several sections of the slope on the north side of the roadway above SR 14, between milepost 73.16 and 73.92 have a history of rockfall, especially in fall and winter months. To reduce the risk of rock fall and mitigate slope stability, contactors crews from Strider Construction Co., Inc., will…
Project

SR 14 - 1.7 Miles East of Bingen - Slope Stabilization

Timeline: April 2021 - Summer 2022
  • Road
  • Construction
  • Klickitat County
Several sections along State Route 14 have a history of reoccurring rockfall activity above the roadway. To help reduce future potential rockfall activity and improve safety for travelers, in summer 2021, our contractor, James Dean Construction, Inc. began work to stabilize the slope located on the…
Project

SR 14 - E of Bingen – Port of Klickitat Access Improvements

Timeline: Spring 2015 - Summer 2025
  • Rail
  • Road
  • Pre-construction
  • Klickitat County
To reduce the potential for an increase in delays and connectivity issues, WSDOT in partnership with BNSF, are working to design and construct an improved rail crossing that will reduce backups along SR 14 due to train traffic and increase safety and connectivity between Bingen Point, the Port of…
Project

SR 14 - I-205 to SE 164th Avenue Auxiliary Lanes

Timeline: Fall 2017 - Spring 2024
  • Road
  • Construction
  • Clark County
With more traffic using State Route 14 than ever before, this project will construct new lanes of travel on both directions of SR 14 between I-205 and Southeast 164th Avenue in Vancouver to help ease congestion and improve travel reliability.
Project

SR 16 - SR 160 - Kitsap County Fish Passage Barriers - Remove Fish Barriers

Timeline: Summer 2023 - Fall 2025
  • Road
  • Pre-construction
  • Kitsap County
There are two opportunities to learn more about this upcoming fish barrier removal project. WSDOT is hosting both an online and in-person open house to share plans on removing fish passage barriers in Salmonberry Creek and Blackjack Creek. See additional information below in "What to Expect.…
Project

SR 16 and SR 302 (SPUR) Purdy Creek - Remove Fish Barriers and Paving

Timeline: 2022-2024
  • Road
  • Construction
  • Pierce County
This project improves habitat and passage for fish in Purdy Creek under SR 302 and SR 16.
Purdy Creek attempts to flow under SR 16 inside 40-year-old culverts. Unfortunately, the fish cannot navigate the old culverts. This project will remove and replace the old culverts with large bridge…
Major Project

SR 160 - Fauntleroy Terminal - Trestle & Transfer Span Replacement

Timeline: Winter 2020 - TBD
The SR 160 - Fauntleroy Terminal - Trestle & Transfer Span Replacement project will replace the aging Fauntleroy ferry terminal to maintain safe and reliable ferry service for people who travel between West Seattle, Vashon Island, the Kitsap Peninsula and beyond. The terminal faces several…
Project

SR 161 - Unnamed Tributaries to Hylebos Creek - Fish Passage

Timeline: Spring 2021 - Fall 2026
  • Road
  • Pre-construction
  • King County
Three culverts carrying tributaries to Hylebos Creek near Federal Way will be replaced with new structures under SR 161 that do not create a barrier to fish. This work builds on our commitment to remove fish barriers on streams that run under state highways.
Project

SR 164 - East Auburn Access

Timeline: This project is on hold, awaiting further coordination among agency partners
  • Road
  • Pre-construction
  • King County
SR 164/Auburn Way South provides primary access to the Muckleshoot Indian Reservation and growing areas of east Auburn. The Muckleshoot Indian Tribe is leading this project to reduce congestion, increase safety, and accommodate growth on the SR 164 corridor from SR 18 to the Poplar Street curve.
Project

SR 164 - Pussyfoot Creek - Fish Passage

Timeline: June 2021 - Fall 2022
  • Road
  • Construction
  • King County
This project built a bridge for SR 164 over Pussyfoot Creek on the Muckleshoot Indian Reservation east of Auburn. This opens an additional 9.3 miles of habitat for salmon and other fish. The old culvert had conditions that make it difficult or impossible for fish to travel upstream.
Project

SR 165 - South of Fairfax Bridge - Emergency Repair

Timeline: Winter 2022 - Fall 2022
  • Road
  • Not started
  • Pierce County
This project will make repairs to State Route 165 south of Carbonado in Pierce County. The highway has experienced settlement, dips and shoulder-drop-offs and washouts as a result of winter storm system that brought heavy rains on January 7. An emergency contract will be issued for this repair work…
Project

SR 166 - Bethel/Bay/Maple Intersection - Roundabout

Timeline: Spring 2023 - Fall 2023
  • Road
  • Pre-construction
  • Kitsap County
The existing traffic signal at the Bethel/Bay/Maple intersection has reached the end of its useful life. Following research and analysis, WSDOT proposes to replace the existing traffic signal with a modern single-lane roundabout.
Project

SR 167 - SR 410 to SR 18 NB Congestion Management

Timeline: Spring 2021 - Summer 2022
  • Road
  • Construction
  • Pierce County
Travelers on northbound State Route 167 between Puyallup and Auburn experience regular congestion, especially during morning peak commute hours. To help reduce delays during peak commute hours, WSDOT is building a new northbound high occupancy vehicle lane on SR 167. The new HOV lane will begin…
Project

SR 167 Completion Project

Timeline: 2015-2028
  • Road
  • Construction
  • Pierce County
The SR 167 Completion Project in Pierce County is part of the Puget Sound Gateway Program, which also includes the SR 509 Completion Project in King County. Together these projects complete two major unfinished highways in the Puget Sound region to create new connections to Interstate 5, the ports…
Project

SR 167 Corridor Improvements Project

Timeline: We are advancing preliminary engineering and environmental work to be construction ready.
  • Road
  • Pre-construction
  • King County
The SR 167 Corridor Improvements Project is comprised of the SR 167 Toll Equipment Upgrade Project and the SR 167, SR 516 to South 277th Street Southbound Auxiliary Lane Project. As part of the SR 167 Toll Equipment Upgrade Project, we plan to update the SR 167 toll system to create consistency…
Project

SR 167/SR 516 to S 277th Street – Southbound Auxiliary Lane

Timeline: TBD
  • Road
  • Not started
  • King County
WSDOT plans to construct an additional one mile of general-purpose capacity by adding an auxiliary lane on southbound SR 167 between SR 516 and South 277th Street in Kent. The project aims to address operational challenges and will be constructed using existing shoulder pavement.
Project

SR 169 - Ravensdale Creek - Fish Passage

Timeline: Summer 2021- Fall 2022
  • Road
  • Construction
  • King County
In 2021 and 2022, between Maple Valley and Black Diamond we will replace the culvert that carries Ravensdale Creek under SR 169, along with two other nearby culverts. The existing culverts are narrow, which forces the water through too quickly for salmon and other fish to continue upstream.
Project

SR 17 - Grape Drive Intersection Improvements

Timeline: Spring 2021 - Fall 2022
  • Road
  • Construction
  • Grant County
This project will remove the existing signal at the intersection and build a multilane roundabout on SR 17 at the intersection of Grape Dr. Construction is scheduled to be complete September 2022.
Project

SR 18 - Issaquah/Hobart Rd to Deep Creek - Widening

Timeline: 2019 - late 2020s
  • Road
  • Pre-construction
  • King County
SR 18 is a crucial highway connecting the south Puget Sound area with I-90, the state's main east-west route. SR 18 has experienced frequent congestion and collisions for decades.

We are receiving construction funding from the 2022 Move Ahead Washington transportation package…
Project

SR 18 - Weyerhauser Way to SR 164 - Barrier Replacement - Complete Novemeber 2021

Timeline: July 2021- Fall 2021
  • Road
  • Completed
  • King County
In 2021 we replaced an aging concrete barrier and screens that reduce headlight glare between the eastbound and westbound lanes on SR 18 between Weyerhaeuser Way and SR 164 in Auburn.
Project

SR 20 - Campbell Lake Road - Intersection Improvements

Timeline: 2016 - Present
  • Road
  • Not started
  • Skagit County
The Samish Indian Nation is partnering with WSDOT and Skagit County to develop a practical solution to improve safety and access at the intersection of SR 20 and Campbell Lake Road.
Project

SR 20 - Deception Pass and Canoe Pass Bridges - Painting and Special Repairs - Complete Fall 2021

Timeline: Fall 2018 - Fall 2021
  • Road
  • Completed
  • Island County
  • Skagit County
The Deception Pass Bridge and Canoe Pass Bridge connect Whidbey Island to the rest of Washington state via State Route 20. These bridges provide the only land access on and off the island. Crews last gave these bridges a fresh coat of paint more than 20 years ago. The years of wind, sun and…
Project

SR 20 - Fish Creek & Lorenzan Creek - Fish Passage

Timeline: 2021
  • Road
  • Construction
  • Skagit County
This project provides for the improvement of fish passage in two locations along SR 20 in the town of Concrete, located in Skagit County - one at Fish Creek (MP 87.82) and one at Lorenzan Creek (MP 88.78) by replacing existing culverts with two buried fish passage structures.
Project

SR 202 Skunk Creek and SR 203 Unnamed Tributaries to Snoqualmie River - Fish Passage

Timeline: Spring 2021 - Fall 2026
  • Road
  • Pre-construction
  • King County
As part of the state's fish recovery efforts, WSDOT has made it a priority to reconnect waterways where roads act as barriers. In Western Washington, that means replacing culverts and building hundreds of fish-passable structures under state highways by 2030 to create more habitat which is…
Project

SR 202/Sammamish River fish passage

Timeline: Fall 2021 – Summer 2023
  • Road
  • Pre-construction
  • King County
Two culverts near the intersection of State Route 202 and Northeast 124th Street between Redmond and Woodinville will be replaced with a single culvert. Two creeks in the area — an unnamed tributary of the Sammamish River and High School Creek — will be realigned to merge with the new, larger…

We are hiring!

We have a range of positions open across the state - view all current job openings.

Improved access to 98.2 miles of upstream fish habitat

through 15 fish passage projects in 2021.

28% increase in the value of exports and imports 

from $90.2 billion in 2020 to $115.5 billion in 2021.