US 2 and SR 21 - Wilbur – Paving & Complete Streets

Project overview

This project will rehabilitate the asphalt for both US 2 and SR 21 within the town limits of Wilbur in Lincoln County to preserve the roadway structure and the public investment in highways. Along with repaving the roadway, the Complete Streets screening process found this project is subject to WSDOT’s Complete Streets requirement to implement elements of Complete Streets for US 2 and SR 21 in the Town of Wilbur.

Timeline
Spring 2025 - Summer 2027
Project status
Pre-construction
Funding
$4.6 Million
Project hotline

What to expect

This project is in the final stages of pre-design, where Complete Streets improvements are being identified and advanced for inclusion in the corridor paving project. The addition of Complete Streets strategies to the paving project aims to improve the active transportation environment along and across the project corridors.  

The full design is expected to start in July 2026 and continue through the end of 2026. This project will be delivered using the Design-Bid-Build process, with construction anticipated to begin in the summer of 2027. This schedule is preliminary and may change depending on the results of the pre-design phase.

Zoomed out map view locating the Wilbur project limits.

US 2 and State Route (SR) 21 within the Town of Wilbur have been identified as needing their asphalt concrete pavement rehabilitated to preserve the roadway structure and the public investment in highways. The original scope of this project involved rehabilitating the existing pavement with a hot mix asphalt pavement and upgrading basic safety features within the project limits to maintain safe highway operations. 

 In 2022, the Washington State Legislature added a Complete Streets requirement in RCW 47.04.035, which instructs WSDOT to incorporate principles of Complete Streets into transportation projects with an estimated budget greater than $500,000 and starting design on or after July 1, 2022 (increased to $1 million for projects beginning design on or after August 1, 2025). To aid in the implementation of this requirement, WSDOT established a Complete Streets process that first screens all programmed projects for Complete Streets applicability and subsequently provides a planning and conceptual design phase – known as pre-design – and target outcomes for projects that are required to incorporate Complete Streets. More information about the Complete Streets requirement and WSDOT’s implementation process is available on WSDOT’s Complete Streets page. 

The Complete Streets screening process found the Wilbur paving project for US 2 and SR 21 to require implementation of the Complete Streets requirement. Complete Streets has been analyzed during the pre-design phase on US 2 from NW Portland St to the Dollar General Store and from US 2 to SW Prince St on SR 21. The pre-design phase included the following tasks: 

  • Coordination with local and regional jurisdictions
  • Identification of Complete Streets opportunities
  • Community engagement
  • Development and prioritization of Complete Streets alternatives
  • 30% design of prioritized alternatives
  • Documentation&

 Community engagement 

The WSDOT project team enjoyed the opportunity to connect with the Wilbur community in several ways since the pre-design began in early 2025: 

  • Wilbur Wild Goose Bill Days booth
  • Community-wide project introduction mailer
  • Opportunities and preferences online survey
  • Public workshop
  • Project update mailer
  • Prioritization online survey

 These opportunities focused on understanding walking, biking, and rolling preferences and travel patterns, which helped WSDOT in developing Complete Streets strategies along and across US 2 and SR 21 in Wilbur and in understanding community priorities. 

Complete Streets opportunities analysis  

Analysis of collected traffic counts posted speed limits and observed travel speeds, number of lanes, and existing bicycle and pedestrian facilities is used to calculate the Level of Traffic Stress (LTS) rating for bicycles and pedestrians. LTS is a measurement of how comfortable a roadway is for bicyclists and pedestrians, where LTS 1 is comfortable for everyone and LTS 4 is only comfortable for a very small portion of the population. WSDOT’s standards require Complete Streets projects to develop strategies that achieve LTS of 1 or 2 for both bicycles and pedestrians. LTS at WSDOT currently applies only to along a roadway. The project team identified potential crossing locations for modifications based on safety characteristics, land uses, ability to implement, socio-economic and demographics, and opportunities identified by the community.  

The following maps show the existing bicycle and pedestrian LTS ratings for the project corridors.

Image
A map of the Town of Wilbur, highlighting the areas around US Highway 2 and State Route 21. The map features a light yellow background that outlines the major streets, secondary roads, and landmarks. Main roads are indicated with broader lines, while local roadways are thinner. The map includes a railroad depicted with a gray line and features a few notable locations such as the Dollar General and school fields.
Map 1: Existing Bicycle Level of Traffic Stress  
Image
A map of the Town of Wilbur, showing the layout of streets and pedestrian conditions along US 2 and SR 21. The map includes various colored lines and symbols indicating different types of roadways and pedestrian levels of service (LTS). A railroad is marked on the map, represented by a black line. Local roadways are depicted with thin lines, while state routes are bolder. The pedestrian levels vary from very low (LTS 1, in blue) to high (LTS 4, in red).
Map 2: Existing Pedestrian Level of Traffic Stress 

The following map shows the existing posted speed limits for the project corridors.

Image
A map of the Town of Wilbur, located at the intersection of US 2 and State Route 21. The map is oriented with the north at the top, indicated by a small arrow. It features a light yellow background representing the town area, with various streets depicted in thin black lines. Main roads are labeled, including US 2 and SR 21, which are highlighted in thicker lines—US 2 in red and SR 21 in yellow.  Several local streets are shown, including Cliff Ave, Front Ave, and Division St.
Map 3: Existing Posted Speed Limits