Project overview
In early 2027, WSF will replace the major mechanical and electrical systems of the vehicle transfer span at our Anacortes, Lopez and Orcas terminals. The transfer span is the part of the slip that raises and lowers to meet up with the ferry to allow vehicles to drive on and off. These transfer span lift systems have been in operation for several decades, (Lopez-1981, Orcas-1987/1999, Anacortes-1993) and are at the end of their lifespans. The slip cannot function while its major components are being replaced. Because of this, we will have 48-hour service closures at our Coupeville, Lopez Island and Orcas Island terminals, which operate from a single slip. Anacortes has two slips, so we can operate from one while upgrading the other.
Vehicle reservations will be blocked on closure dates. Please mark your calendars early and sign up for WSF Rider Alerts to receive updates as project dates approach.
What to expect
Why are full closures necessary?
The items of the transfer span to be replaced – lift beam, head frame, counterweights, and cables – are major structural and mechanical components of the ferry slip. The slip cannot operate without them. Also, the contractor’s equipment must be in the slip to perform the work.
These upgrades improve safety for our crews and reliability for our passengers and standardize operations for terminal and vessel staff who rotate among our terminals. For speed and efficiency, WSF will sequence this work to move from one terminal to the next to keep consistency of work crews and minimize passenger disruption.
Upcoming ferry service changes for construction:
- Anacortes single slip operations, Monday-Friday, Feb. 22-26
- Orcas Island 48-hour closure, Tuesday and Wednesday, March 9-10
- Lopez Island 48-hour closure, Tuesday and Wednesday, March 16-17
- Coupeville 48-hour closure, Tuesday and Wednesday, March 23-24
Description of the work that will take place during the 48-hour shutdown
- New lift beam will have hydraulic pins that replace ones that are currently operated with a manual lever. This system matches those used at other terminals allowing for operational consistency and improved safety for terminal staff.
- New headframe allows us to use larger counterweight cables, which boost system safety. This headframe will also support a landing at the top for a new ship’s ladder.
- New counterweights and cables. Shorter counterweights that will be less likely to sit in the water at high tide.
- Larger counterweight cables for added safety.
- New live load hanger bars that align with the new hydraulic pins being installed.
Orcas Island terminal showing headframe and other mechanical elements to be replaced during the transfer span update.
To arrive at the closure dates, we conducted extensive community outreach in the San Juan Islands and in Island County and considered these factors: community input, events, school schedules, holidays, ridership numbers, seasonal weather conditions, tidal closures, in-water work dates and contractor availability.