SR 4 - Skamokawa Vic to 0.3 Miles West of SR 432 - Chip Seal and Highway Modifications

Project overview

In summer 2021, contractor crews working for WSDOT will resurface roughly a 25-mile stretch of State Route 4, between Skamokawa and State Route 432 near west Longview, between mileposts 29.77 to 54.98.

Timeline
May 2021 - Fall 2021
Project status
Construction
Funding
$4.7 Million

What to expect

Once construction begins, travelers should expect weekday, daytime single lane closures with flaggers and a pilot car leading travelers through the work zone. Travelers should plan for delays of up to 20 minutes. Bicyclists will be transported through the work zone when present. Any highway closures will be announced in advance. 

As with any highway construction project, travelers must exercise caution. Traveling at slower speeds decreases the chance of damage from rocks which may be thrown up from other vehicles. Please be patient when traveling in work zones. Traveling at the posted construction speed limit in construction zones will ensure your safety and the safety of highway workers. 

In summer 2021, contractor crews working for WSDOT, will repair and resurface a nearly 25-mile stretch of SR 4, between mileposts 29.77 to 54.98, just west of Longview, WA.