As of Sunday, Nov. 1 at 7:30 p.m., all major construction has concluded for 2026. People should still expect some overnight closures and lane reductions on mainline I-5 and the express lanes for bridge maintenance and drainage improvements on the underside of the Ship Canal Bridge.
Starting Monday, Nov. 2, at 5 a.m. the express lanes will revert to their regular operating schedule.
Project overview
WSDOT built Interstate 5, Washington’s main freeway, in the 1960s. The busiest section runs through Seattle with almost 240,000 vehicles traveling across the I-5 Ship Canal Bridge daily. This critical highway now requires major preservation and repairs.
Working with our contractor, Atkinson Construction, we have prioritized repairs on the I-5 Ship Canal Bridge, which last had a major preservation effort about 40 years ago.
Through the Revive I-5: Ship Canal Bridge Preservation project, WSDOT will repair and resurface the upper bridge deck, replace concrete and aging bridge expansion joints, improve drainage and address other maintenance issues. Major construction will continue over the next two years, ending in 2027. This planned preservation effort will help extend the life of the bridge and prevent more unplanned traffic disruptions.
What to expect
Northbound I-5 weekend-long full closure
Crews are removing the Ship Canal Bridge work zone the weekend of Oct. 30-Nov. 2, weather permitting, activities include reconfiguring lanes, picking up pinned barriers and restriping lanes and shoulders.
The weekend-long full closure extends from I-90 to Northeast 45th Street and begins at 11:59 p.m. Friday, Oct. 30, to 5 a.m. Monday, Nov. 2.
The following on-ramps to mainline northbound I-5 will be closed as early as 9 p.m. Friday, Oct 30, to 5 a.m. Monday, Nov. 2:
- South Dearborn Street
- Cherry Street
- University Street
The following on-ramps to mainline northbound I-5 will be closed as early as 10 p.m. Friday, Oct 30, to 5 a.m. Monday, Nov. 2:
- Westbound I-90
- Olive Way
- Mercer Street
The following on-ramps to mainline northbound I-5 will be closed as early as 11 p.m. Friday, Oct 30, to 5 a.m. Monday, Nov. 2:
- Eastbound I-90
- Harvard Avenue East
- Westbound State Route 520
The following mainline northbound I-5 off-ramps will be closed as early as 11:59 p.m. Friday, Oct 30, to 5 a.m. Monday, Nov. 2:
- Seneca Street
- Olive Way
- Mercer Street
- Lakeview Boulevard East
- Eastbound SR 520
- Northeast 45th/Northeast 50th Street
Available exits
Those who reach the closure point when traveling northbound can exit to:
- I-90
- South Dearborn Street
- James Street
- Madison Street
- Edgar Martinez Drive South
Or enter the express lanes from mainline I-5 around Seattle’s Chinatown-International District (entrance on the left). There are additional express lane entrances from downtown Seattle. The express lanes do have height restrictions and some ramps may be HOV-only.
The first exit from the express lanes is Northeast 42nd Street in the University District. There is no access to SR 520 from the express lanes. Express lanes return to mainline I-5 at Northgate.
Express lanes
Once the work zone is removed, the express lanes will return to its regular schedule, switching directions each day and closing overnight. Crews may require some additional express lanes closures in 2026 to complete work this season. When major construction begins in 2027, express lane operations will be southbound only 24 hours a day.
2027
In 2027, expect months-long reductions of southbound I-5 lanes across the Ship Canal Bridge. Crews will again need weekend-long full directional closures of I-5 to install and remove the work zones. We will share more specific details closer to the planned work.
Know before you go
You can expect delays during periods of construction on the Ship Canal Bridge. Plan ahead and give yourself extra time to travel.
We encourage you to ride transit – it’s the best, most reliable way to get around – and youth 18 and under ride free. If you’re planning on traveling to and from Seattle, refer to the available transit resources in our Related links tab.
The two right lanes of northbound I-5 are closed across the Ship Canal Bridge until the end of 2026. The express lanes are northbound-only 24 hours a day.
The Ship Canal Bridge is critical to the region, moving almost 240,000 vehicles each day. The bridge is 60 years old and the deck has not seen a preservation effort in 40 years; it is showing signs of significant deterioration. WSDOT completed more than 200 emergency repairs on the bridge between 2019 and 2024, work that was unplanned and unexpectedly affected traffic throughout the region.
We’re setting the stage for long-term work to preserve the lifeline that I-5 has become for our region. We know that I-5 connects people to their jobs, families, and communities, and it keeps our economy moving. That’s why, even as we focus on this critical work now, we’re already planning for the next steps to keep the entire corridor safe and reliable for generations to come.