Project overview
The driving surface along a 2.2-mile stretch of southbound I-5 from Northeast 179th Street (milepost 9.75) to the I-5/I-205 split (milepost 7.55) was bumpy, uneven and in need of repair.
Contractor crews began work in late April 2026 to remove damaged concrete panels and resurface the roadway with 9 inches of asphalt across all lanes and shoulders. Crews used a crack, seat and overlay method to break the worn concrete pavement into smaller pieces, press them into place to create a stable base, and pave a new layer of asphalt on top. The project also included replacing guardrail, installing new signage and upgrading stormwater treatment facilities.
With this work complete, travelers can now enjoy a smoother, more reliable ride along this stretch of southbound I-5.
What to expect
Travelers can now expect a smoother ride on southbound I-5 between Northeast 179th Street and the I-5/I-205 split. Concrete panel replacement work is now underway just north, between Ridgefield/Pioneer Street and Northeast 179th Street, to address damaged areas and prepare the roadway for the next phase of improvements. In summer 2027, crews will return to rehabilitate another 4 miles of southbound I-5 using the same crack, seat and overlay method. Together, these coordinated projects will improve more than 6 miles of southbound I-5 in Clark County.
Image shows the location of work to repair and repave a 2.2-mile stretch of southbound I-5 between Northeast 179th Street and the I-5/I-205 split in northern Clark County.
Built in 1969, this 2.2-mile stretch of southbound I-5 between Northeast 179th Street and the I-5/I-205 split was originally constructed with concrete panels. Over time, traffic and weather have damaged many panels, creating a rough ride for travelers.
This section contains about 8,400 concrete panels, many 50 to 70 years old and well beyond their expected lifespan. Replacing all of them at once would be costly and disruptive, so WSDOT focused on fixing the worst panels first.
Recent improvements
Summer 2022–2023: Concrete panel replacement
WSDOT contractor crews replaced roughly 100 concrete panels along both directions of I-205 between the Glenn Jackson Bridge near the SR 14 interchange and the I-5/I-205 split, as well as along southbound I-5 between Northeast 179th Street and the split. The work also rehabilitated bridge joints on several I-205 bridges to extend their lifespan and improve the driving surface. This work prepared the roadway for future pavement improvements but did not fully address the rough driving conditions. To help warn travelers about the uneven surface, crews installed “Rough Road” and speed advisory signs.
Fall 2025:
Crews returned to replace the “worst of the worst” panels. More than 80 panels were replaced. Drivers may still notice a bumpy ride, but the most damaged panels have been replaced.
Summer 2026: Crack, seat and overlay project
Crews rebuilt 2.2 miles of southbound I-5 between Northeast 179th Street and the I-5/I-205 split using the crack, seat and overlay method. The process breaks the existing concrete pavement into a stable base before crews add new asphalt on top to create a smoother, more durable roadway.
Fall 2026: Additional concrete panel replacement
Crews will replace the most damaged concrete panels along 4 miles of southbound I-5 between Pioneer Street and Northeast 179th Street. These repairs will address the roughest areas and prepare the roadway for the next phase of improvements.
Looking ahead
In summer 2027, crews will return to rebuild approximately 4 miles of southbound I-5 using the same crack, seat and overlay method. This long-term pavement improvement will create a smoother, more durable driving surface for travelers.