Project overview
Travelers on Interstate 405 between Renton and Bellevue experience one of the state’s worst commutes. The I-405/Renton to Bellevue Widening and Express Toll Lanes project includes multimodal transportation and safety improvements to offer more reliable travel choices and keep drivers, transit riders and freight moving.
The Renton to Bellevue project will add new capacity to create a two-lane ETL system between SR 167 in Renton and Northeast Sixth Street in Bellevue. In general, the project will add one new lane in each direction and combine the existing HOV lane with the new lane to create a dual ETL system.
The new ETLs will connect to the existing express toll lane system between Bellevue and Lynnwood, as well as the SR 167 HOT lanes via the I-405/SR 167 Interchange Direct Connector, to create a 40-mile ETL system. This project is designed to improve speeds and trip reliability for all travelers and support the new I-405 Bus Rapid Transit (BRT) line between Lynnwood and Tukwila included in the voter-approved Sound Transit 3 package.
What to expect
Southbound I-405 in Renton closed overnight for barrier placement, Feb. 9-10
Travelers should plan for a full closure of southbound Interstate 405 in Renton from Feb. 9-10. Crews will be placing barriers.
Closure details
Southbound I-405 in Renton will be closed from North Southport Drive/Sunset Boulevard Northeast to State Route 167 from 11:59 p.m. Monday, Feb. 9 to 4 a.m. Tuesday, Feb. 10. A signed detour route will be in place.
The following on-/off-ramps will be closed:
- SR 169/SR 900 on-ramp to southbound I-405
- Southbound I-405 off-ramp to SR 515/Talbot Road South (Exit 3)
- Southbound I-405 off-ramp to southbound SR 167/Auburn/Rainier Avenue South (Exit 2)
- Southbound I-405 direct connector ramp to SR 167
“Know before you go," travel during off-peak hours or, if possible, delay discretionary travel to help minimize backups.
Work is dependent on good weather and may be rescheduled. Schedule updates will be available on the project webpage, WSDOT’s Travel Center map, the WSDOT mobile app and by signing up for King County email updates.
Upcoming work
Week of Feb. 1 – Feb. 7
Impactful work adjacent to I-405:
- Bridge 11 investigation and installing temporary illumination (5 nights: 2/2-2/6).
- Installing a temporary separate storm sewer system on Southcenter Boulevard (5 nights: 2/2-2/6).
- Rebar delivery on Southeast Eighth Street (1 night: 2/2).
City of Bellevue:
- Installing sign structures at the northbound I-405 off-ramp to eastbound I-90 (4 nights: 2/3-2/6).
- Paving at the westbound I-90 on-ramp to northbound I-405 (4 nights: 2/3-2/6).
- Installing sign structures and barrier, performing embankment work and cap demolition on northbound I-405 between Lake Washington Boulevard Southeast and I-90 (1 nigh: 2/2).
- Installing sign structures, performing cap demolition, and fiber work on northbound I-405 between Southeast Eighth Street and Northeast Fourth / Eighth Street (3 nights: 2/3-2/5).
- Performing fiber work on northbound I-405 between Southeast Eighth Street and Northeast Fourth / Eighth Street (1 night: 2/6).
- Performing fiber work at the Southeast Eighth Street on-ramp to northbound I-405 (2 nights: 2/3-2/4).
- Performing fiber work at the northbound I-405 off-ramp to Northeast Eighth Street (2 nights: 2/3-2/4).
- Performing fiber work at the Northeast Fourth Street on-ramp to northbound I-405 (1 night: 2/5).
- Survey work at the northbound I-405 off-ramps to SR 520 (1 night: 2/2).
- Survey work at the northbound I-405 off-ramps to SR 520 (1 night: 2/6).
- Conducting barrier survey at the Northeast Fourth Street on-ramp to southbound I-405 (1 night: 2/2).
- Installing barrier, performing civil work, barrier grading, surveying, and installing sign structures on southbound I-405 between Southeast Eighth Street and I-90 (2 night: 2/5-2/6)
- Installing barrier on southbound I-405 between I-90 and Northeast Fourth Street (3 nights: 2/2-2/4).
- Installing barrier at the Northeast Sixth Street on-ramp to southbound I-405 (3 nights: 2/2-2/4).
- Installing a sign structure at the Southeast Eighth Street on-ramp to southbound I-405 (2 nights: 2/5-26).
- Repairing potholes near the southbound I-405 off-ramp to eastbound I-90 (1 night: 2/5).
- Performing civil work on westbound Coal Creek Parkway Southeast (5 nights: 2/2-2/6).
- Installing a truck mounted attenuator on eastbound Southeast Eighth Street near I-405 (1 night: 2/2).
- Proofing and pulling fiber on northbound I-405 near Bridge 40ETL (4 nights: 2/2-2/5).
City of Newcastle:
- None planned.
City of Renton:
- Boring, installing sign structures, and restriping on northbound I-405 between SR 181 and SR 169 (5 nights: 2/2-2/6).
- Mobilizing equipment on northbound I-405 between the I-5 and SR 169 (1 night: 2/2).
- Paving, restriping on northbound I-405 between the I-5 off-ramp and SR 169 off-ramp (1 night: 2/6).
- Restriping at the Sunset Boulevard North on-ramp to northbound I-405 (1 night: 2/6).
- Restriping at the northbound I-405 off-ramp to SR 900 / North Southport Drive (1 night: 2/6).
- Installing cast-in-place barrier at the northbound I-405 off-ramp to Northeast 30th Street (1 night: 2/5).
- Paving, installing a sign structure and noise wall panels at noise wall 5 (5 nights: 2/2-2/6).
- Installing a sign structure and paving at the Northeast 30th Street on-ramp to southbound I-405 (1 night: 2/4).
- (MOT 73, 74) Installing conduit, restriping, grading barrier, and installing a sign structure at the SR 169 / SR 900 on-ramp to southbound I-405 (5 nights: 2/2-2/6).
- Restriping on southbound I-405 between the SR 169 off-ramp and Talbot Road South off-ramp (3 nights: 2/4-2/6).
- Boring and restriping near wall 3.30L (3 nights: 2/4-2/6).
- Installing sign structures on southbound I-405 between SR 900 and SR 181 (2 nights: 2/2-2/3).
- Installing conduits, junction boxes, and directional bores on the Bronson Way North on-ramp to southbound I-405 (4 nights: 2/2-2/5).
- Installing illumination conduits and junction boxes at the southbound I-405 off-ramp to North Southport Drive (4 nights: 2/2-2/5).
- Installing cast-in-place barrier on northbound I-405 near Exit 6 (5 nights: 2/2-2/6).
Week of Feb. 8– Feb. 14
Impactful work adjacent to I-405:
- Installing sign structures on northbound and southbound SR 167 between South 43rd Street and I-405 (4 nights: 2/9-2/12).
- Bridge 11 investigation and installing temporary illumination on northbound and southbound SR 181 (4 nights: 2/9-2/12).
- Performing work on Northeast 44th Street (5 nights: 2/9-2/13).
City of Bellevue:
- Installing sign structures at the Coal Creek Parkway Southeast on-ramp to northbound I-405 (2 nights: 2/9, 2/11).
- Clearing and grubbing at the eastbound I-90 off-ramp to Factoria Boulevard (4 nights: 2/9-2/12).
- Removing temporary barrier and paving at the westbound I-90 on-ramp to northbound I-405 (2 nights: 2/10, 2/12).
- Installing bores, embanking, installing sign structures and demolishing sign caps, paving, conducting work at wall 10.36IR, and installing drainage on northbound I-405 between Coal Creek Parkway Southeast and North Sixth Street (1 night: 2/9).
- Distributing fiber and installing bores, temporary barrier, fiber, and sing structures on northbound I-405 between Southeast Eight Street and Northeast Fourth / Eighth Street (3 nights: 2/10-2/12).
- Installing fiber at the northbound I-405 off-ramp to Northeast Fourth / Eighth Street (3 nights: 2/9-2/11).
- Installing fiber at the Southeast Eighth Street on-ramp to northbound I-405 (2 nights: 2/9, 2/12).
- Installing fiber at the Northeast Eighth Street on-ramp to northbound I-405 (1 night: 2/10).
- Performing a survey and installing fiber at the northbound I-405 off-ramp to eastbound and westbound SR 520 (1 night: 2/12).
- Installing fiber at the Northeast Fourth / Eighth Street on-ramp to southbound I-405 (1 night: 2/11).
- Installing fiber and a sign structure on southbound I-405 between Southeast Eighth Street and I-90 (1 night: 2/12).
- Installing concrete panels, sign structures, and drainage on southbound I-405 between milepost 13.35 and milepost 10 (3 nights: 2/9-2/11).
- Working on the Northeast Sixth Street HOV on-ramp to southbound I-405 (3 nights: 2/9-2/11).
City of Newcastle:
- Paving the southbound I-405 off-ramp to Northeast 44th Street (1 night: 2/12).
City of Renton:
- Installing directional bores on southbound I-405 near South Third Street (4 nights: 2/9-2/12).
- Installing illumination conduits and junction boxes at the southbound I-405 off-ramp to North Southport Drive (4 nights: 2/9-2/12).
- Installing cast-in-place barrier at the northbound I-405 off-ramp to Northeast 30th Street (5 nights: 2/9-2/13).
- Installing drainage and restriping on northbound I-405 between SR 181 and SR 169 (4 nights: 2/9-2/12).
- Installing a sign structure and restriping on northbound I-405 between I-5 and SR 169 (2 nights: 2/10-2/11).
- Installing illumination conduits and restriping at the northbound I-405 off-ramp to SR 900 (2 nights: 2/10-2/11).
- Restriping at the North Southport Drive on-ramp to northbound I-405 (2 nights: 2/10-2/11).
- Restriping, work at wall 6.50, and installing cast-in-place barrier on northbound I-405 between milepost 6.1 and milepost 7 (2 nights: 2/9, 2/12).
- Installing cast-in-place barrier at the northbound I-405 off-ramp to Northeast 30th Street (3 nights: 2/9-2/11).
- Installing fiber and sign structure, paving, and installing panels for noise wall 5 (3 nights: 2/10-2/12).
- Paving the southbound I-405 off-ramp to Sunset Boulevard Northeast (1 night: 2/12).
- Installing temporary barrier and sign structures, and work at wall 4.28 (3 nights: 2/10-2/12).
- All lanes of southbound I-405 will be fully closed for work overnight (1 night: 2/9).
Project improvements will occur in the Renton to Bellevue area along I-405.
Travelers on Interstate 405 between Renton and Bellevue experience one of the state’s worst commutes. The I-405/Renton to Bellevue Widening and Express Toll Lanes Project includes multimodal transportation improvements to offer more reliable travel choices and keep drivers, transit riders and freight moving.
Project highlights include:
- A new southbound auxiliary lane in the I-90 to 112th Avenue Southeast vicinity.
- Improvements at interchanges, including Northeast Park Drive and Northeast 44th Street in Renton, and 112th Avenue Southeast and Coal Creek Parkway in Bellevue.
- Construction of portions of the King County Eastrail, including a 2.5-mile paved section and a new crossing over I-405 in downtown Bellevue at the site of the former Wilburton rail bridge (in partnership with King County).
- New direct access ramp and inline transit station at NE 44th Street in Renton to help support BRT operations (in partnership with Sound Transit).