Project overview
Travelers on Interstate 405 between Renton and Bellevue experience one of the state’s worst commutes. The I-405/Renton to Bellevue Widening and Express Toll Lanes project includes multimodal transportation and safety improvements to offer more reliable travel choices and keep drivers, transit riders and freight moving.
The Renton to Bellevue project will add new capacity to create a two-lane ETL system between SR 167 in Renton and Northeast Sixth Street in Bellevue. In general, the project will add one new lane in each direction and combine the existing HOV lane with the new lane to create a dual ETL system.
The new ETLs will connect to the existing express toll lane system between Bellevue and Lynnwood, as well as the SR 167 HOT lanes via the I-405/SR 167 Interchange Direct Connector, to create a 40-mile ETL system. This project is designed to improve speeds and trip reliability for all travelers and support the new I-405 Bus Rapid Transit (BRT) line between Lynnwood and Tukwila included in the voter-approved Sound Transit 3 package.
What to expect
Upcoming work
Week of March 8-14
Impactful work adjacent to I-405:
- Restriping on SR 181 near bridge 11 (5 nights: 3/9-3/13).
- Performing civil work and installing drainage along westbound Coal Creek Parkway Southeast (5 nights: 3/9-3/13).
- Performing work along eastbound and westbound Northeast 44th Street (5 nights: 3/9-3/13).
- Performing work on westbound Sunset Boulevard North near bridge 22M (2 nights: 3/9-3/10).
- Potholing along eastbound Sunset Boulevard Northeast (3 nights: 3/11-3/13).
City of Bellevue:
- Paving, installing sign structure, and installing drainage near wall 10.36IR (5 nights: 3/9-3/13).
- Fiber work near the eastbound Northeast Eighth Street on-ramp to northbound I-405 (1 night: 3/10).
- Fiber work near the Northeast 10th Street off-ramps to westbound and eastbound SR 520 (1 night: 3/9).
- Fiber work near the southbound I-405 off-ramp to westbound Northeast Eighth Street (1 night: 3/11).
- Paving and installing sign structure, drainage, and concrete pavement along southbound I-405 between Main Street and I-90 (5 nights: 3/9-3/13).
- Installing cabinet pad near the Southeast Eighth Street on-ramp to southbound I-405 (3 nights: 3/11-3/13).
- Installing sign structure and panels for noise wall 5 on southbound I-405 between Coal Creek Parkway Southeast and the May Creek Bridge (6 nights: 3/9-3/14).
City of Newcastle:
- Installing sign structure, barrier, backfill, and underdrain along northbound I-405 between Northeast 30th Street and Gypsy Creek (5 nights: 3/9-3/13).
- Installing sign structure and panels for noise wall 5 on southbound I-405 between Coal Creek Parkway Southeast and the May Creek Bridge (6 nights: 3/9-3/14).
City of Renton:
- Installing sign structures on northbound I-405 between SR 181 and SR 169 (2 nights: 3/9-3/10).
- Installing sign structure, concrete pavement panels, and barrier near wall 3.30R (3 nights: 3/11-3/13).
- Installing sign structure, barrier, backfill, and underdrain along northbound I-405 between Northeast 30th Street and Gypsy Creek (5 nights: 3/9-3/13).
- Installing backfill and underdrain near the northbound I-405 off-ramp to Northeast 30th Street (5 nights: 3/9-3/13).
- Installing sign structure and panels for noise wall 5 on southbound I-405 between Coal Creek Parkway Southeast and the May Creek Bridge (6 nights: 3/9-3/14).
- Grading barrier along southbound I-405 between Northeast 30th Street and SR 169 (3 nights: 3/11-3/13).
- Installing sign structures near wall 4.28M (2 nights: 3/9-3/10).
- Grading barrier near the SR 169 on-ramp to southbound I-405 (3 nights: 3/11-3/13).
- Vegetation removal near bridge 15 (5 night: 3/9-3/13).
Week of March 15 – March 21
Impactful work adjacent to I-405:
- Restriping on SR 181 near bridge 11 (5 nights: 3/16-3/20).
City of Bellevue:
- Installing sign structure and panels for noise wall 5 on southbound I-405 between Coal Creek Parkway Southeast and the May Creek Bridge (6 nights: 3/16-3/21).
- Up to two lanes of northbound I-405 from I-90 to Northeast Sixth Street will be closed day and night (3 nights: 3/20-3/22).
- Up to two lanes of southbound I-405 from the Northeast Eighth / Fourth Street off-ramp to the Southeast Eighth Street off-ramp will be closed day and night (3 nights: 3/20-3/22).
City of Newcastle:
- Installing sign structure and panels for noise wall 5 on southbound I-405 between Coal Creek Parkway Southeast and the May Creek Bridge (6 nights: 3/16-3/21).
City of Renton:
- Installing sign structure and panels for noise wall 5 on southbound I-405 between Coal Creek Parkway Southeast and the May Creek Bridge (6 nights: 3/16-3/21).
Project improvements will occur in the Renton to Bellevue area along I-405.
Travelers on Interstate 405 between Renton and Bellevue experience one of the state’s worst commutes. The I-405/Renton to Bellevue Widening and Express Toll Lanes Project includes multimodal transportation improvements to offer more reliable travel choices and keep drivers, transit riders and freight moving.
Project highlights include:
- A new southbound auxiliary lane in the I-90 to 112th Avenue Southeast vicinity.
- Improvements at interchanges, including Northeast Park Drive and Northeast 44th Street in Renton, and 112th Avenue Southeast and Coal Creek Parkway in Bellevue.
- Construction of portions of the King County Eastrail, including a 2.5-mile paved section and a new crossing over I-405 in downtown Bellevue at the site of the former Wilburton rail bridge (in partnership with King County).
- New direct access ramp and inline transit station at NE 44th Street in Renton to help support BRT operations (in partnership with Sound Transit).