• Contract

SR 16/SR 302 Spur, Purdy Creek Remove Fish Barriers and Paving

Contract summary

For SR 16 Purdy Creek: Realigning the stream and replacing the existing 6-foot diameter corrugated metal pipe with a two 206-foot prestressed concrete girder bridges.

For SR 302 (Spur) Purdy Creek: Realigning the stream and replacing the existing 6-foot interior span x 6-foot interior rise x 70-foot box culvert with a 77-foot precast prestressed concrete slab bridge. Six hundred fifty working days. Involves one hundred eighty items.

Public Works
Publication Date
Contract status
Advertised
Contract ID
009763
County
Pierce County
Submittal due date and time
Estimated value
Under $30,000,000
Funding source
This is a Federally funded project with a Disadvantaged Business Enterprise Condition of Award Goal: 21%
Contact
Justin Janke
Project Engineer