Contract work has been completed with punchlist items remaining.
This project includes grading, sub-surface material, asphalt base layer, and Portland Cement Concrete Pavement to form about a mile of main freeway lanes. Includes completion of the Freya Street Interchange ramps. This mile of freeway continues the construction series in the 10.5-mile highway. When the NSC fully completed, travel time between Wandermere and I-90 will be reduced to approximately 12 minutes; fewer trucks will be on the local arterials because they will be using the freeway for north and south destination points
All major construction was finished in the summer 2020.
View current construction and traffic impacts.
Financial Data for PIN 600015B | ||||||||||||
|
Bob Hilmes, design project engineer
Mark Allen, construction project engineer
WSDOT Eastern region
2714 N. Mayfair
Spokane, WA 99207
509-324-6000