March 6 project update: Bertha on the move again

Posted on Mar 6 2017 4:35 PM
Seattle Tunnel Partners resumed mining today after conducting additional survey work to verify Bertha’s position and to make necessary adjustments to complete the tunnel drive. Crews performed routine inspections and maintenance while mining was stopped, including the replacement of cutterhead tools.  
 
As of this afternoon, Bertha was tunneling north toward the intersection of Denny Way and Sixth Avenue North, less than 1,000 feet from the disassembly pit. 
 
STP stopped mining on Feb. 28 after survey data indicated the tunneling machine may be several inches off the tunnel alignment. Three independent surveys confirmed the 57.5-foot machine was approximately six inches off alignment.
 
STP designers made a slight change to the tunnel alignment between the machine’s current location and the end of the tunnel drive. Adjustments are common during tunneling, including on this project. STP made a similar adjustment to correct Bertha’s course after the machine mined out of the access pit following repairs. 
 
Crews steer Bertha (links to YouTube) based on information they receive from its onboard guidance system. The system is now set to the new tunnel alignment.
 
According to STP’s most recent schedule, Bertha will arrive at the disassembly pit in May. Progress updates are posted on Mondays and Thursdays at our Follow Bertha page. You can also follow Bertha on Twitter @BerthaDigsSR99.