June 15 project update: New time-lapse video shows tunneling machine disassembly

Posted on Jun 15 2017 2:54 PM

The inner-workings of the SR 99 tunneling machine Bertha are now fully visible from the camera above the pit where disassembly continues. The upper shield that surrounded Bertha is now gone – lifted and hauled away. Only a small portion of the cutterhead spokes remain. Next, Seattle Tunnel Partners plans to remove work-deck platforms, hydraulic systems, hyperbaric equipment and ring-building equipment. Remember, there’s 8,000 tons of machinery inside the disassembly pit and inside the north end of the tunnel. This brief time-lapse video shows what seven weeks of nearly non-stop work looks like as workers continue dismantling the five-story-tall tunneling machine.