Contents tagged with home

  • Jan. 17 project update: Tunneling crews resume mining

    Seattle Tunnel Partners resumed mining late Monday following 10 days of hyperbaric maintenance on Bertha, the SR 99 tunneling machine.
     
    Crews replaced approximately 300 of the nearly 500 scrapers on Bertha’s cutterhead during the hyperbaric maintenance period. As this post explains in more detail, the scrapers line the sides of the cutterhead spokes. STP also conducted other important inspections and maintenance during this time.
     
    Completing routine maintenance is an important part of ensuring that the machine continues to operate properly. STP will continue to perform inspections and maintenance as needed over the remainder of the tunnel drive.
     
    Crews are less than 2,500 feet from the receiving pit near Seattle Center where Bertha will emerge at the end of tunneling. The top of the cutterhead is located approximately 160 feet below Third Avenue in Belltown. 
     
    Progress updates are posted on Mondays and Thursdays at our Follow Bertha page. You can also follow Bertha on Twitter @BerthaDigsSR99.
     
    — more —

    Order: 1

  • Jan. 13 project update: Hyperbaric work continues

    Seattle Tunnel Partners is making good progress as they continue performing hyperbaric maintenance on Bertha, the SR 99 tunneling machine. Since the maintenance period began on Jan. 5, crews have replaced 250 cutterhead tools (see example below) over the course of 184 hours of hyperbaric shifts. This maintenance is critical as STP prepares for the final 25 percent of the tunnel drive.  
     
    Some of the cutterhead tools replaced during this maintenance stop
     
    The work is taking place in the chamber behind Bertha’s cutterhead, as shown in this image (PDF). As the video below explains, working in this environment is similar to performing an underwater dive.  
     
     
    STP will resume tunneling when the maintenance period is complete. The top of Bertha’s cutterhead is located approximately 160 feet below Third Avenue, about halfway between Blanchard and Bell streets. Crews are less than 2,500 feet from the receiving pit near Seattle Center where Bertha will emerge.
     
    Progress updates are posted on Mondays and Thursdays at our Follow Bertha page. You can also follow Bertha on Twitter @BerthaDigsSR99.
    — more —

    Order: 1.1

  • Jan. 5 project update: Bertha reaches next planned maintenance stop

    During the holiday break, Seattle Tunnel Partners performed routine maintenance and inspections on Bertha, the SR 99 tunneling machine. This included inspection of some of the machine’s cutterhead tools under normal atmospheric pressure. STP decided to begin a hyperbaric maintenance stop this week to inspect the other cutterhead tools on the machine under hyperbaric conditions (this post explains the different types of tools in more detail).  
     
    Crews plan to spend between one and two weeks inspecting the tools, and replacing them as necessary. However, the duration of the stop could be longer or shorter depending on the number of tools that need to be replaced. STP’s most recent hyperbaric maintenance stop in late October lasted one week. 
     
    The top of the cutterhead is located approximately 160 feet below Third Avenue, about halfway between Blanchard and Bell streets. Crews are less than 2,500 feet from the receiving pit near Seattle Center where Bertha will emerge at the end of her tunnel drive.
     
    Progress updates are posted on Mondays and Thursdays at our Follow Bertha page. You can also follow Bertha on Twitter @BerthaDigsSR99.
     
    — more —

    Order: 1.2

  • #99closure feature: Drone footage inside the SR 99 tunnel

    Just a few days before the SR 99 tunneling machine started tunneling under the Alaskan Way Viaduct, the Washington State Department of Transportation flew a video-equipped drone through the SR 99 tunnel to show Seattle Tunnel Partners’ construction progress. There has been continued interest in seeing what has been built below ground and this video gives a glimpse of the tunnel as well as the nooks and crannies of the complex tunneling machine.

    On an average day, the tunnel is … more

  • The choreography of a concrete pour

    This week, at the south entrance to the bored tunnel, Seattle Tunnel Partners is pouring concrete for a section of the future southbound highway. On one hand, the pouring of concrete (also known as a "concrete placement”) is nothing extraordinary – it’s a common occurrence on a project that will use enough concrete to build nine football stadiums. But their frequency belies the complex choreography that goes into executing each pour successfully. Since concrete plays … more

  • Take a virtual tour of SR 99 tunnel construction

    Keeping the public informed about our work to replace the Alaskan Way Viaduct is an important part of what we do every day. Our goal is to give you as much access as possible to this amazing project, which is why we regularly post updates, photos and videos of our progress. We even offer walking tours from our information center, Milepost 31, to a viewing platform that overlooks the pit where tunneling began in summer 2013.

    Unfortunately, there’s one frequently received request … more

  • New narrated video explains Bertha repair work

    As reported elsewhere on our website, work to access and repair the SR 99 tunneling machine is coming along. We’ve heard from some people that Seattle Tunnel Partners’ repair plan is hard to picture. Enter STP’s Chris Dixon, who was nice enough to narrate a video that explains what crews are doing to resume tunneling by March 2015. Watch it on YouTube or download a WMV file.

    Other resources 

    Seattle Tunnel Partners repair work plan (pdf 4.8 Mb) … more

  • What we’re doing to keep traffic moving during the four-day SR 99 closure

    We’ve been asking you to do your part to reduce congestion when SR 99 closes for four days starting Friday night, Aug. 22. That includes things like changing your commute habits and choosing an alternate way to get around.

    But what are we, the agencies tasked with keeping traffic moving during this closure, doing to help? Quite a bit, actually. Here’s a roundup of some of the steps we’re taking to help you and your fellow commuters through the closure.

    Washington … more

  • Traffic shift underway on State Route 99 near the stadiums

    Less than three years ago, crews demolished the southern mile of the Alaskan Way Viaduct. When they did, they shifted traffic onto a new section of State Route 99 south of downtown Seattle.

    Much of that new section of SR 99 is permanent, but the piece west of the stadiums is temporary. This curving stretch of road takes drivers around the SR 99 tunnel construction site and connects to the remaining section of the viaduct near South King Street. It’s nothing fancy, but it’s … more

  • Celebrate Bike Month on our new path

    Just in time for Bike Month, we opened a new permanent connection between the on-street bike lanes south of South Atlantic Street and the shared-use path from South King Street. Here’s a map that shows the improvements, which include:

    A dedicated, 14-foot-wide shared-use path with improved paving.

    Improved lighting.

    A separate northbound and southbound path for more efficient navigation.

    Signs warning of vehicles crossing the intersection of … more