Early warning: Four-day closure of SR 99 coming in late August

Posted on Jul 11 2014 12:07 PM

In August, crews working on the North Access contract near the SR 99 tunnel’s north portal will demolish the bridge on SR 99 over Broad Street. Not sure what bridge we’re talking about? Don’t worry. Even the most seasoned SR 99 commuter may not realize they are crossing a bridge at Broad Street.

That bridge, and Broad Street itself, must be completely transformed to make room for the future connection to the tunnel’s north portal and on- and off-ramps at Harrison and Republican streets.

Crews have already begun to fill in Broad Street with recycled concrete from the former roadway. Once we close this section of SR 99 to traffic, crews will bring in heavy equipment and demolish the old bridge in about 12 hours. They’ll then spend the next two days adding more fill material to make the new roadway level with the existing lanes of SR 99. After paving the new SR 99 roadway, crews will stripe the lanes and reinstall barriers. Once all of this is completed, SR 99 will reopen.

Closure information
Demolishing a bridge and building a new road in its place isn’t easy work. It is especially challenging on a major highway through Seattle. To minimize disruptions to drivers, crews will replace this portion of SR 99 in a mere four days. Drivers should plan ahead for SR 99 closures from Friday night, Aug. 22 to Wednesday morning, Aug. 27.  View a map of the closure. 

  • From 10 p.m. Friday, Aug. 22 to 5 a.m. Monday, Aug. 25 SR 99 will be closed in both directions from the West Seattle Bridge to Valley Street.
    • Northbound SR 99 will be open from South Royal Brougham Way until midnight on Friday, Aug. 22 for exiting Seahawks traffic.
  • From 5 a.m. Monday, Aug. 25 to 5 a.m. Wednesday, Aug. 27 SR 99 will be closed in both directions from the south end of the Battery Street tunnel to Valley Street.

There’s a lot of other work that will happen on SR 99 during this closure as well, including utility work at Harrison Street, concrete panel replacement in SODO, expansion joint repairs on the viaduct near the Seneca Street off-ramp and removal of ivy and other maintenance on the viaduct.

We will continue to share information to help drivers plan ahead and get around during the closure.