Construction Highlights for Friday, June 13 - Friday, June 20

Posted on Jun 14 2014 3:46 PM

SR 99 Corridor

Friday, June 20 – Monday, June 23
  • Crews will close all lanes of northbound SR 99 between South Spokane Street and Valley Street from 10 p.m. Friday to 5 a.m. Monday.
Saturday, June 21 – Monday, June 23
  • Crew will close the left lane of southbound SR 99 between Thomas and Republican streets from 4 p.m. Saturday to 5 a.m. Monday.
Friday, June 20
  • Crews will close the right lane of northbound SR 99 between the south end of the Battery Street Tunnel and Republican Street from 1 a.m. to 6 a.m. Friday.

Regional

Friday, June 20 – Monday, June 23
  • Crews will close both directions of SR 520 between Montlake Boulevard Northeast and I-405 from 11 p.m. Friday to 5 a.m. Monday.

North

Long-term closures

  • Crews have reduced Dexter Avenue North to one lane in each direction around the clock between Roy and Thomas streets.
Tuesday, June 17 – Thursday, June 19
  • Mercer Corridor Project crews will reduce Mercer Street to one lane in each direction between Fifth Avenue North and Dexter Avenue North from 8 p.m. to 5 a.m. each night.  

Central

Through June 19
  • Crews working for Puget Sound Energy will close southbound Occidental Avenue South around the clock between Yesler Way and South Washington Street.

South

Long-term closure
  • Seattle City Light crews will reduce First Avenue South by one lane in each direction between South Atlantic Street and Railroad Way South from 9 a.m. to 3 p.m. on weekdays, and from 7 a.m. to 4 p.m. on weekends. Crews will not close lanes on days with major events at the stadiums.