Skip Top Navigation

US 395 - North Spokane Corridor

Status

November 2009

Why is WSDOT building the North Spokane Corridor?

This project addresses the need for a major improvement to allow motorists and freight to move through metropolitan Spokane along the corridor from I-90 to US 395 at Wandermere.  The needs of the corridor are indicated by increasing congestion and other operational and safety issues on the existing street network.  The project will provide a facility for balanced transportation including park and ride lots to support transit and vanpooling operations, as well as an expanded and enhanced pedestrian/bicycle facility. Right of way will also be reserved for future high-capacity transportation.

The End Result

When completed, the North Spokane Corridor will be a 60-mile per hour, limited access highway with a direct connection to I-90 just west of the existing Thor/Freya Interchange.  Other interchanges will be placed at locations such as Trent Avenue (SR 290), Wellesley Avenue, Francis / Freya Street, Parksmith Drive, US 2, and US 395 at Wandermere.  

 

Project Benefits
Consider the following benefits:

  • Able to travel between Wandermere and I-90 in less than 12 minutes. 
  • A free flowing facility which doesn't have conflicts with schools, parks, shopping areas, or pedestrians, but has reasonable access to these areas.
  • Fewer trucks will be on the local streets because they will use the freeway for north/south through movements.
  • Cleaner air because you aren't stopping at intersections along the way.
  • A safe pedestian/bike corridor which connects to other established bikepaths as well as the neighborhoods along the way.
  • Increased jobs due to construction spending in the community and increased economic vitality.

What is the project timeline?
 

  • In April 1997 the Final Environmental Impact Statement, six years in preparation, was completed by WSDOT and approved by the Federal Highway Administration (FHWA).
  • Summer 2000, approval of the Limited Access and Right-of-Way Plans and also approval by FHWA of a Supplemental Environmental Impact Statement for the Spokane River to Wanderemere section.
  • On August 22, 2001, construction began on the first construction element, a grading and drainage contract, from the vicinity of Hawthorne Road to US 2.  The project was completed in July, 2002.
  • A Design/Access Hearing was held on February 26, 2003 for the I-90 to the Spokane River section. 
  • An environmental re-evaluation of the April 1997 FEIS document was approved in May, 2005 by the FHWA. The Findings and Order was adopted in July, 2005 and the final limited access was established in October, 2005.
  • July 2003, $189 million appropriated through nickel increase in gasoline tax. Two projects to be built, Francis Avenue to Farwell Road and US 2 to Wandermere and US 2 Lowering.
  • 2005-$152 million allocated from the Transportation Partnership package for the North Spokane Corridor.
  • 2009-$28 million was allocated by the Legislature for re-design and right of way aquisition from the Spokane river to Francis Avenue.
    August 22, 2009-Two-lane segment from Francis/Freya to Farwell opened to traffic.

How long will it take to build the NSC?

This is a frequently asked question.  The answer is:  It depends on funding commitments from the State of Washington and the Federal Highway Administration.  See the Financial Information section below for current funding levels.  Because future funding levels are unpredictible, the exact construction project schedule cannot be determined.

Financial Information
 

  • Current Project Funding - The design, construction, and right-of-way projects that are currently underway are funded through the following sources:
  • Federal Funding - $18 million
  • State Funding - $559 million
  • Total Funding Available From All Sources - $577 million

        - - - - - - - -

  • Overall Corridor Funding Status as of July 2009 - Since 1990, through the environmental, design, right-of-way acquisition, and construction phases, the WSDOT has been allocated $577 million.  Of that amount $284 million has been expended in those categories. 
  • Remaining Corridor Estimated Project Cost - $1.6 billion in 2008 dollars.  Over a 20-year build out plan with estimated risk and inflation variables included the cost is $3.0 billion.  These values are subject to price escalation due to market trends in commodities (oil, steel, concrete), construction costs, real estate prices, etc. 

- - - - - - - - -

  • Estimate Revisions - WSDOT revises these estimates on an annual basis with a risk assessment process and adjusts them accordingly.

How can I get more information?
Contact:
Project Engineer Larry Larson P.E.
WSDOT Project Office
2714 N. Mayfair
Spokane, WA 99207
Phone: (509) 324-6091
E-mail: SR395NSC@wsdot.wa.gov

back to top