US 2 - I-5 Interchange to Bickford Ave Vic - Paving

Project News

  • This weekends's closure of westbound US 2 has been POSTPONED.
  • The work has been rescheduled: Westbound US 2 now will be closed from the SR 204 interchange to just east of the 20th Street Southeast ramp starting at 7 p.m. Friday, June 1 to 4 a.m. Monday, June 4.
  • This is the first of six weather-dependent weekend closures of westbound US 2.
  • Sign up to receive email updates about this project and other Snohomish County topics.
     

Overview
Contractor crews with Lakeside Industries will repave three miles of the westbound lanes of US 2 from Bickford Avenue to the I-5 interchange, including the Hewitt Avenue trestle. The eastbound lanes will be resurfaced from the US 2/SR 204 interchange to Bickford Avenue.

Why is WSDOT rehabilitating the existing pavement on roughly three miles of US 2 in Everett?
This stretch of highway hasn’t been repaved since 2002. The asphalt used during that project was identified as having an average lifespan of about 15 years. Since then, cracks, ruts and potholes have developed. This creates an uneven surface which allows water to pool on the roadway. Wet roads create difficult driving conditions and can also result in slower travel times as drivers reduce their speeds to handle the slick surface. Installing new pavement will also extend the life of the highway.

Westbound weekend closures
When crews remove the pavement in the westbound lanes, they will take the opportunity to also inspect the trestle and make any necessary repairs. This process requires more space and time than an overnight lane reduction allows, so the inspection and repairs will happen during six westbound weekend closures of the US 2 trestle.

This work is weather dependent. It is tentatively scheduled from 7 p.m. Friday to 4 a.m. Monday on the following weekends:

  • June 1 – June 4
  • June 22 – June 25
  • June 29 – July 2
  • July 13 – July 16
  • July 20 – July 23
  • Dates to be announced

The eastbound trestle is newer and made of concrete, so it does not require weekend closures. Work on eastbound US 2 between the SR 204 interchange and Bickford Avenue will happen overnight.

The End Result
This project will make this section of US 2 safer for the 22,000 drivers who use it daily. New pavement also reduces future maintenance needs and costs.

Needs & benefits

  • Safety: Repaving the highway removes existing cracks, ruts and potholes where pooled water can collect, causing cars to slide. This water can also freeze, creating pockets of ice on the asphalt. New pavement will also prevent future damage to the roadway.
  • Economic: Repairing aging asphalt is a cost-effective way to protect the roadway and increase its lifespan.

Timeline

  • April 2018: Construction began.
  • Spring/summer 2018: Weekend closures scheduled.
  • Fall 2018: Construction scheduled to be completed.

Funding

Financial Data for PIN 100201P, 100210G
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $7,865
CWA $0
Total $7,865

 
Contact

Frances Fedoriska
WSDOT Communications
Phone: 206-440-4690
Email: Fedorif@wsdot.wa.gov

A map of the repaving area from US 2/I-5 to Bickford Avenue.

Existing rutting and cracking on westbound US 2 trestle.
Example of some of the existing rutting and cracking on the westbound US 2 trestle heading toward the I-5 interchange.