US 12 - Frenchtown Vicinity to Walla Walla - Add Lanes

Quarterly Project Report Update for Quarter Ending December 2006

Project Title & Location
US 12 - Frenchtown Vicinity to Walla Walla - Add Lanes
Walla Walla County

Project Description
This project is phase six of eight phases that improve US 12 from SR 124 (Burbank) to Walla Walla. This approximately eight mile project will reconstruct US 12 from McDonald Road to Walla Walla as a four lane divided highway, with improved capacity and enhanced safety.

Contractor/Consultant
David Evans and Associates prepared the Resource Reports.  Landau and Associates is studying the springs near Pine Street. 

Recent Progress

WSDOT continues to progress in design of the Pine Street Interchange and roundabouts at the interchange.  We have acquired 8 parcels and have offers on 15 other properties. Two of the four residential relocations are complete.

Design Construction Impacts

Recent cost escalations have increased the construction amount of this project by approximately 22%.  This $14 million dollar increase had been incorporated into WSDOT's 2007-2009 Budget request to the Governor.  A majority of these increases can be attributed to rising fuel prices and asphalt oil used to make hot mix asphalt pavement.  

Environmental Impacts / Compliance

The NEPA and SEPA Documentation was complete the first of November.  Negotiations for wetland mitigation and permitting are continuing.

Impacts to Traffic

A majority of the project work will take place away from existing roadways.  To keep traffic moving and increase safety at the Pine Street Intersection, WSDOT will construct a temporary detour which will allow traffic to maintain highway speeds.

Project Milestones Scheduled Attained Milestone Outlook
PE Start April 05 July 05 Preliminary Design work began under US 12 - Wallula to Walla Walla Planning Study.
Environmental Documentation May 06 Nov 06 NEPA and SEPA were complete in November 2006
Right of Way Certification Oct 06 Due to additional work associated with Pine Street Interchange and property acquisition in the Frenchtown Monument area, Certification will occur by October 2007.
Contract Advertisement Nov 06

Due to additional work associated with Pine Street Interchange and property acquisition in the Frenchtown Monument area, WSDOT proposes to advertise in Fall 2007.

Operationally Complete June 09 No impacts anticipated
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  3.1  6%
Right-of-Way $  7.0 14%
Construction $40.3 80%
Funded Project Costs $ 50.4 100%

Nickel funds included in above costs

$1.4  3%

2005 Transportation Partnership Account

$36.0 71%

  For more information, go to www.wsdot.wa.gov/projects

Kerry Grant, WSDOT Project Engineer
(509) 577-1760 or grantk@wsdot.wa.gov

Project Cost Summary reflects the March 2006 Approved Legislative Supplemental Budget