WSDOT Projects

text size: T T T

SR 520 Bridge Project - Common Questions

General
Tolling
Funding
Accelerated project schedule
Environment
Noise
Transportation - Vehicles, Transit, Bike/Ped, Boats
Quick facts about the existing SR 520 bridge
Floating Bridge Facts
Getting Involved
 

General

SR 520 is a vital link across Lake Washington, carrying more than 115,000 vehicles and 155,000 people east and west each day. Since its construction in the early 1960s, the Portage Bay Bridge and the floating Evergreen Point Bridge and approach structures have aged. They are susceptible to catastrophic failure in the event of an earthquake or windstorm. Improvements have kept the bridges safe and functional, but the bridges won’t last forever.

The hollow bridge columns are as vulnerable to earthquakes as the Alaskan Way Viaduct. The floating bridge is vulnerable to wind and waves. The drawspan, anchor cables and pontoons could break or crack during windstorms, and the bridge could sink.

Where is the project site?
The project extends along the SR 520 corridor from I-5 in Seattle to 108th Avenue NE on the Eastside (just west of I-405). The project also includes minor improvements to eastbound SR 520 between I-405 and 124th Avenue NE.

View a map of the project area.

What will replace the SR 520 bridge?
WSDOT will replace the existing four-lane bridge with a new six-lane bridge that includes two high-occupancy vehicle (HOV) lanes. It also will include a bicycle/pedestrian path and five lidded areas covering the highway to reconnect neighborhoods.

How was the plan selected?
In 2006 Gov. Chris Gregoire issued the Path Forward to Action: Findings on the Alaskan Way Viaduct and SR 520 Projects, in which she endorsed the “4+2” replacement, four general-purpose lanes and two HOV lanes, as the most viable alternative for the SR 520 corridor.

Her endorsement came after an expert review panel extensively reviewed the project’s draft environmental impact statement, recalculated cost information and weighed public comments. During the 2007 legislative session, the state legislature passed into law engrossed substitute Senate Bill (ESSB) 6099, which also endorsed the 4+2 replacement as the best choice for building a new bridge. WSDOT is completing a supplemental draft EIS, which will include more information about construction effects and mitigation, pontoon construction and west-side design.

What other alternatives were considered?
A four-lane bridge replacement was analyzed in the August 2006 draft EIS. This alternative is not being pursued further because it would not improve mobility in the corridor. More information about the four-lane alternative can be found in the draft EIS.

Early analysis of other alternatives found that the volume of traffic flowing across an 8-lane bridge replacement would create additional backups on an already congested I-5. To accommodate the additional traffic, significant improvements to I-5 would be necessary. An additional study in 2003 found that, even with tolls, expensive improvements to I-5 would still be necessary in order to reduce the expected backups onto I-5.

What is the No-Build Alternative?
All environmental impact statements include a "no-build alternative" as a comparison to the proposed build alternatives evaluated in the document. Typically, the no-build alternative assumes that the highway would remain the same as it is today. However, because the fixed spans of the Portage Bay and Evergreen Point bridges are aging and are vulnerable to earthquakes, and the floating portion of the Evergreen Point Bridge may sink in a windstorm, there is a reasonable probability that these bridges will not be usable in 2030 (the analysis year for the EIS). Two no-build scenarios were evaluated in the draft EIS: the continued operation scenario, and the catastrophic failure scenario.

How will the plan save time for commuters?
The new HOV lanes will improve traffic flow and save commuters time by reducing congestion for carpools, vanpools and buses. Wide shoulders will allow a safe place for disabled vehicles to safely pull off the highway. With disabled vehicles moved out of traffic, emergency vehicles can arrive sooner, and traffic is less interrupted.

Will the new bridge have a bike path?
Yes, the replacement project will include a bicycle/pedestrian path (pdf 906 kb) along the SR 520 corridor, safely separated from the highway.

Will the 4+2 replacement include high-capacity transit?
The new SR 520 bridge will accommodate high-capacity transit, most likely in the form of bus rapid transit. Transit agencies are responsible for determining transit service in the SR 520 corridor.

See the draft high-capacity transit plan (pdf 3.7 mb) for more information.

How much does the project cost?
The 2006 estimate for the 4+2 bridge replacement, including the Pacific Street Interchange, is $4.38 billion.

Estimated cost savings from accelerating the project schedule and reducing the number of pontoons ranges from $500 million to $700 million.

The projected new cost* of the project is $3.7 - $3.9 billion.

*This projected cost estimate could change based on the conclusions and design options included in the project impact plan due to Gov. Gregoire and the state legislature in December 2008.

 

Tolling

Will tolls be used as a way to fund the SR 520 Bridge Replacement and HOV Project?
The legislature has directed WSDOT to examine tolling as a way to fund the project. WSDOT updated the project’s finance plan (pdf 621 kb), which includes several tolling scenarios and analysis on the amount of funding that could be generated.

Gov. Gregoire recently signed House Bill 1773, authorizing tolls in Washington state, and House Bill 3096, authorizing tolls on SR 520. House Bill 3096 also creates a tolling implementation committee to work with the public to evaluate a variety of tolling scenarios.

How will tolls be collected?
Modern toll-collection technology has made tollbooths a thing of the past. Drivers will pay tolls without stopping, using a vehicle-mounted transponder and electronic overhead readers mounted in roadway structures over each lane. The readers will recognize individual transponders and deduct the toll from the driver’s prepaid account. Cameras equipped with license-plate reading technology could be used to collect tolls from vehicles that are not equipped with transponders. Today transponder technology and license-plate recognizing cameras are being used as part of WSDOT’s Good to Go! program to toll the new Tacoma Narrows Bridge.

Was the original Evergreen Point Bridge tolled? Yes, the Evergreen Point Bridge was tolled from the time it was completed in August 1963, until it was paid off in June 1979. The tolls generated approximately $60 million.

 

Funding

How is this project funded?
This project is funded through a combination of state and federal money. Tolling is also expected to contribute to project costs.

Funding Source

Amount

State gas tax

         $554 million

Allocation from WSDOT "risk pool"

 $1,072 million

Previously committed federal bridge funds

$114 million

State sales tax deferral or transfer

$180 million

Funding from tolls

 

Tolls on the new SR 520

$850 million - $1,520 million

Tolls on the existing bridge

$480 million - $570 million

Tolling on I-90

To be determined

Total Funding

$3,250 million - $4,010 million

*This projected cost estimate could change based on the conclusions and design options included in the project impact plan due to Gov. Gregoire and the state legislature in December 2008.
 

Accelerated project schedule

What is the new project timeline?
2008 - Complete mediation process; submit project impact plan.

2009 - Begin pontoon construction at existing site; purchase 45 new buses for corridor.

2010 - Begin construction of new pontoon construction site.

2011 - Complete corridor environmental process; begin pontoon construction at new site.

2012 - Begin corridor construction on both sides of Lake Washington; begin floating bridge construction.

2014 - Open new bridge to drivers.

2016 - Open six-lane corridor to drivers.

2018 - Project complete.

How can you complete the project in less time?
We will be able to accomplish this accelerated schedule through the following actions:

  • Using innovative contracting approaches.
  • Streamlining the environmental process.
  • Advancing pontoon construction.
  • Accelerating construction in the SR 520 corridor.
  • Finalizing the project finance plan, including the possible contribution from tolls.

What has been accomplished so far?
2006 - Released the draft environmental impact statement and held two public meetings to gather public comments; an Expert Review Panel reviewed project cost estimates and implementation plan; Gov. Gregoire selected the six-lane bridge in a 4+2 configuration.

2007 - Mediation process begins; independent review of alternative project options begins; continued working with Eastside communities to develop designs that would improve community connections; draft high-capacity transit plan released.

2008 - New project finance plan released; project team continues to develop floating bridge and Eastside design; mediation group identifies three west side design options to be further evaluated in the supplemental draft environmental impact statement; Gov. Gregoire announces accelerated project schedule; Gov. Gregoire signs bills authorizing tolls statewide (House Bill 1773) and establishing a tolling implementation committee for SR 520 (House Bill 3096).

Does the new schedule mean you have to leave things out of the project?
No, we did not change the design of the project or the associated improvements to the 4+2 corridor to meet the new schedule.

Is it going to cost more to get the bridge finished earlier?
No. In fact, an accelerated schedule will result in cost savings. The current project cost with the Pacific Street Interchange is estimated at $4.38 billion. By starting work earlier and using a single row of pontoons, we estimate we can save $500 million to $700 million, bringing down the total projected costs to $3.7 billion to $3.9 billion.

Why is the governor taking action now?
The current SR 520 bridge is vulnerable to windstorms and earthquakes. Gov. Gregoire determined the region needs a safer and more reliable SR 520 before 2018, and asked WSDOT to find ways to open the new bridge earlier.

Do you still expect to hire a contractor before the SR 520 Pontoon Construction Project's environmental process is complete?
WSDOT is still interested in using the innovations of the contracting/construction community to help us deliver the project. We are looking at how and when we'll involve the contracting community.

What is the Pontoon Construction Project timeline?
We plan to complete the environmental process with a Record of Decision in 2009, secure necessary permits and begin building a facility in 2010, and start pontoon construction at the new facility by 2011.

How does using the existing pontoon construction facility in Tacoma affect the number of pontoons and jobs needed at Grays Harbor?
At this time, we do not know how the work will be divided between the existing facility and the proposed new facility. Since pontoons for the SR 104 Hood Canal Bridge Replacement Project are currently under construction in Tacoma, we know this facility has the necessary means to construct pontoons. However, this facility can only produce a limited number of pontoons at a time, and therefore a new facility is still needed to meet our timeline.

We will continue to evaluate how many pontoons can be built at the existing facility and will inform the community when we know more.

Are you looking for sites other than the property at the Port of Grays Harbor for pontoon construction?
We are currently identifying the range of alternatives we will evaluate in our environmental impact statement (EIS). We are considering alternate locations for a new pontoon construction facility, and will advance the locations that appear viable for full study in our EIS. So far, the Port of Grays Harbor property is the only location we've identified for further study in the EIS. We expect to identify the full range of alternatives for the EIS by June 2008.

If alternative locations or new information about previously considered locations is brought to our attention, we will review the viability of these locations. If they meet our needs for catastrophic failure recovery planning, we will evaluate them in the EIS. The proposed alternate locations are mainly sites that we have already considered.

How will you identify and mitigate for potential environmental effects from the Pontoon Construction Project?
We are evaluating potential environmental effects through the environmental review process. We expect to release the draft EIS for the Pontoon Construction Project in early 2009.

We are consulting with resource agencies and Tribal nations to develop a process to evaluate all activities associated with developing a new facility, and constructing and storing pontoons. 

Environment

Will the SR 520 project improve the environment?
The project will include a number of features that will improve conditions over the current SR 520 facility:

  • There will be stormwater treatment facilities to ensure stormwater from the highway meets the latest water quality regulations.
  • New sound walls will substantially reduce noise levels for neighboring communities.
  • The new bridge will have fewer columns (250 feet apart compared to today’s 100 feet).
  • The R.H. Thomson Freeway “ramps to nowhere” near the Washington Park Arboretum will be removed.
  • There will be a new bicycle/pedestrian path across Lake Washington.
  • Sections of the road will be covered by a grassy lid at 10th Avenue E and Delmar Ave E, and Montlake Boulevard in Seattle, and at Evergreen Point Road, 84th Avenue NE and 92nd Avenue NE on the Eastside to improve connections between neighborhoods.

How can I learn more about how the project will affect the surrounding natural and manmade environment?
The project proposes a wider bridge than what exists today. It is wider because it includes HOV lanes, shoulders and a new bicycle/pedestrian path. Some environmental effects linked to construction of a wider bridge will be temporary, while other effects could be longer lasting.

You can learn more about the temporary and permanent environmental effects in our draft environmental impact statement (EIS). Topics covered in the draft EIS include how construction of a wider SR 520 bridge could affect wetlands, parks, fish and wildlife, highway noise, air quality, neighborhoods, navigation channels in Lake Washington, and cultural and historic resources.

Will the project restore, enhance or preserve the areas of the environment that are disrupted by the project?
Yes, restoring the environment is integral to and inseparable from the project. That means the project team is working with tribal nations and state and federal regulatory agencies to make sure the project obtains necessary permits and complies with national and state environmental requirements such as the National Environmental Protection Act (NEPA) and State Environmental Protection Act (SEPA) requirements.

 

Noise

How will this project affect traffic noise in the neighborhoods near SR 520?
To reduce future traffic noise throughout the SR 520 corridor, proposed noise walls, ranging from 8- to 18-feet tall, would extend along the reconstructed SR 520 in Seattle and on the Eastside. Nearly all neighborhoods adjacent to SR 520 will experience less traffic noise. View planned noise wall heights and locations: Seattle, Eastside.

Will highway noise be reduced in nearby SR 520 neighborhoods when the project is complete?
Residents in most neighborhoods along the corridor east and west of Lake Washington will hear less noise once the project is built; however, some neighborhoods will not notice a reduction in highway noise. Noise levels in Laurelhurst/Webster Point and North Capitol Hill will remain virtually the same.

Are there any neighborhoods that will experience increased highway noise once the project is built?
Yes, one section of Bellevue, east of I-405 along NE 24th Street, might experience noticeable increases in highway noise.

Because this part of NE 24th Street is located on a hillside above SR 520, traffic engineers are unable to reduce noise levels with sound walls.

Will the project use "quieter" pavement?
WSDOT is currently studying different forms of quieter pavement to determine whether they would be effective here and is working with the Federal Highway Administration to receive approval for using them. A new test section of quieter pavement was installed on the east side of Lake Washington in July 2007. Track the results alongside WSDOT.

 

Transportation - Vehicles, Transit, Bike/Pedestrian, Boats Does the new bridge benefit all commuters?

The 4+2 bridge replacement will benefit bicyclists, pedestrians, HOV users, and transit riders in the following ways:

  • A new bicycle/pedestrian path will run along the north side of the bridge, connecting Montlake and the University District to the Eastside near Bellevue.
  • New HOV lanes from the I-5/SR 520 interchange to the existing HOV lanes east of I-405 will reduce traffic congestion.
  • Improved transit stops will help make travel faster and more reliable.

Will SR 520 remain open to traffic when the new bridge is under construction?
Yes. The existing floating bridge will remain open while the new floating bridge is under construction.

The new bridge will be built to the north of the existing bridge. WSDOT currently recommends that the west approach of the Evergreen Point Bridge be constructed using a separate detour bridge. The detour bridge could be built to the south of the existing structure. Once completed, both directions of traffic would be shifted to the detour bridge, allowing the existing west approach to be used as a work bridge for the new facility. After the new structures are complete, traffic will move to them, and the detour bridge and old SR 520 floating bridge will be removed. The Lake Washington Boulevard ramps will likely be closed during construction.

Will traffic be able to cross Portage Bay when the new bridge is under construction?
Yes. WSDOT is considering the use of temporary work bridges to the north and south of the existing facility over Portage Bay. A work bridge would be built to the north in order to build the north half of the new facility. Then, the existing bridge would be removed and the south half of the new bridge would be constructed. Once the south half is completed, traffic would be shifted from the new north half to the new, fully constructed bridge and the work trestle will be removed.

Will the navigation channels be in the same locations as today, allowing most types and sizes of pleasure boats to cross on both the east and west side of Lake Washington?
The new bridge will reduce clearance for boat traffic from 44 feet to 25 feet on the west side of Lake Washington. The east side clearance will be increased from 57 feet to 70 feet, matching the clearance of the I-90 bridge. There will be no mid-span opening as there is today. Sailboats and very large motorboats and yachts will be unable to cross under the west end of the bridge but will be diverted to the east navigation channel. Most motorboats will continue to pass under the bridge on the west side. View a diagram of existing and future boat clearances.

 
Quick facts about the existing SR 520 bridge

What is the official name of the floating bridge?
The official name of the SR 520 floating bridge is the Governor Albert D. Rosellini Bridge.

How wide is the current bridge?
The current bridge is 60 feet wide.

How long is the floating section of the bridge?
The floating section of the SR 520 bridge is 1.42 miles (2,285 meters) long, making it the longest floating bridge in the world.

How many pontoons support the current bridge?
The current bridge is supported by 33 bridge pontoons. Each pontoon is about as long as a football field (360 feet) and 16 feet tall.

How many anchors hold the pontoons in place?
The bridge pontoons are held in place by 62 anchors attached with 2-3/16 cables. (Anchors on the pontoons that connect with the east and west approaches require thicker cables. Those cables are 2-3/4" inches thick.)

How much do the anchors weigh?
A standard achor for the SR 520 bridge pontoons weighs 77 tons, which is more than 10 male African elephants.

How deep is Lake Washington?
Lake Washington is 200 feet deep under the drawspan of the current floating bridge. The deepest point in Lake Washington is 214 feet deep.

When did the existing bridge open?
We opened the existing bridge to traffic on Aug. 28, 1963.

How long did the tolls last when the bridge opened in 1963?
We ended tolling on the existing bridge on June 22, 1979, less than 16 years after the bridge opened.

How many vehicles use the current bridge each day?
Every day, approximately 115,000 vehicles use the SR 520 bridge to cross Lake Washington.

How many vehicles did we expect to cross the existing bridge each day when we designed it?
The current bridge was designed to carry 65,000 vehicles per day.

What windspeed was the existing bridge designed to withstand?
The existing bridge was designed to withstand 50-70 mph winds.

Why do you close the bridge to traffic during severe windstorms?
We close the bridge to traffic in order to open the drawspan, which relieves pressure on the bridge from wind and wave action during windstorms.

The criteria for closing the bridge to traffic and opening the drawspan is 50 mph gusts sustained for 15 minutes. When a 40 mph gust is sustained for one minute, a warning alarm alerts crews to come to the bridge for inspection and monitoring.

As with all WSDOT bridges, our experienced crews can close the bridge anytime they deem it unsafe, or when there is a potential for damage.

You can check current conditions at the SR 520 bridge on the Web. 

What repairs and retrofits have been made on the current bridge?
2006 - Replaced drawspan anchor bolts sheared off during storms earlier in the year. The anchor bolts hold the drawspan closed.

2000 - Emergency repairs to column damage.

1998 - Seismic retrofit, cable post tensioning, wave deflectors.

1997 - Pontoon bolts and crack seal.

1993 - Storm damage repair of pontoon cracks.

How many cracks in the bridge pontoons have been repaired?
Crews have repaired more than 30,000 linear feet of cracks since the 1993 Inaugural Day storm.

Floating bridge facts

How do floating bridges float?
Floating bridges are made of large water-tight concrete pontoons connected rigidly end-to-end, upon which the roadway is built. Despite their heavy concrete composition, the weight of the water displaced by the pontoons is equal to the weight of the structure (including all traffic), which allows the bridge to float.

How are floating bridges constructed?
Individual bridge pontoons are usually built on dry land next to a waterway, then floated and towed like barges to the bridge site. They are connected to grounded approach structures on each end, starting at the edge of the floating structure and then pieced together toward the eventual bridge’s center. The pontoons are held in place by enormous steel cables generally hundreds of feet long that are connected to anchors buried deep in the lakebed. For more information and to view an example of a floating bridge under construction, visit the Hood Canal Bridge Project Web site.

Why is WSDOT building a floating bridge over Lake Washington as opposed to a conventional suspension bridge?
A conventional suspension bridge over Lake Washington would not work for several reasons:

  • Suspension bridges need to travel in a fairly straight line. Because SR 520 is a curved corridor, a suspension bridge would not be possible.
  • Lake Washington is between 200- and 400-feet deep, and the bridge’s support towers would have to be approximately 630 feet in height, nearly the height of the Space Needle, to support the bridge. These massive towers would be out of character with the surroundings because it would create more noise and block views.
  • Conventional fixed bridges, such as the new bridge over the Tacoma Narrows, are expensive to build in deeper waters with soft beds, such as Lake Washington.

Where are other floating bridges?
Washington State is the floating bridge capitol of the world with the four longest and heaviest floating bridges. They are the SR 520 Evergreen Point Bridge, the I-90 Lacey V. Murrow Bridge, the I-90 Homer M. Hadley Bridge, and the SR 104 Hood Canal Bridge.

In 1957, a concrete floating bridge was built across Lake Okanagan at Kelowna in south central British Columbia, Canada. Its floating length is 2,100 feet (640 meters) and its design is very similar to the Lacey V. Murrow Bridge.

The Demerara Harbor Bridge in Georgetown, Guyana, is another floating bridge. It is made of steel pontoon units and extends 6,074 feet (1,851 meters). Norway has two large floating bridges – the Bergsoeysund Floating Bridge in Kristiansund, More og Romsdal and the Nordhordland Floating Bridge. Another long-time floating bridge site is the Galata Floating Bridge in Istanbul, Turkey.

How do earthquakes affect the floating section of the SR 520 bridge?
The floating section of the SR 520 bridge is not affected directly by ground shaking from earthquakes because is built on pontoons that are anchored to the bottom of Lake Washington. Some very deep low-frequency earthquakes can cause a seiche, or a surface wave similar to a tsunami. A seiche in Lake Washington could cause the floating bridge to bend and heave at the lake surface, adding large loads of pressure to the pontoons and anchor systems. A seiche in Lake Washington could also create an underwater landslide that could cause the pontoon anchors to slip or break.

Typically the waves from a seiche create less stress in the pontoons than wind-induced waves from a storm that occurs once every 100 years.

How do windstorms and waves affect floating bridges?
Wind and wave forces are typically the controlling forces in the design of floating bridges. A major factor in wind and wave effects on floating bridges is called the fetch. The fetch is the unobstructed clear distance over the water that wind can travel to the bridge. The longer the fetch, the higher the wind and wave forces will be. In Lake Washington the critical fetch is to the southwest of the bridge, since the largest storms historically come from the southwest. Wind and wave forces cause the pontoons to bend, heave and twist, creating large stresses in the pontoons and anchor system. If a 100-year storm event were to occur, the pontoons are designed to prevent large cracks from developing that would allow water to leak in and sink the bridge.

 

Getting Involved

How has the public been involved in the SR 520 Project?
Public involvement in the SR 520 Bridge Replacement and HOV Project has been and continues to be an essential element of the project. We regularly provide project progress information to the public on our Web site and at public events. To date, our activities have included project-area tours; public meetings and open houses; jurisdictional, community and organizational briefings; committee meetings; community workshops; and neighborhood roundtables.

Public opinion is important to WSDOT. Project planners depend on input from people who live and work near the project site. Comments and feedback from community members, residents, businesses, organizations and jurisdiction leaders help us to design a facility that works for the people who live nearby and/or use the corridor.

How does the project team reach out to minority populations and people with limited English proficiency?
WSDOT uses an array of public outreach methods to identify and inform all people who use the roadway and/or live along the corridor including minority, low-income and limited-English-speaking populations. In addition to working with local community centers, we provide project fact sheets in several languages including Spanish, Russian, Chinese and Vietnamese at all of our outreach events and on our Web site.

WSDOT advertises public outreach events in newspapers published for minority audiences, and project information tables at a variety of locations and community events throughout Seattle and the Eastside. Some of these locations and events include Seattle’s Lunar New Year celebration in the International District, Crossroads Mall, farmers markets on the Eastside and the Central Area Community Festival. In addition, the project team provides American Sign Language interpretation and translation services at all public events upon request. Learn more about the project's core public involvement and agency coordination outreach efforts in Appendix B (pdf 629 kb) of the draft EIS.

Are there still opportunities for the public to get involved?
Yes, the thoughts and opinions of all community members, whether they use the bridge every day or simply work or live near it, are very important to WSDOT. Opportunities to get involved will continue throughout the life of the project. For information on how to contact the project team, visit the Contact Us page. Also visit the Project Calendar for information on upcoming events and to view material from past events.