SR 520 - Bridge Replacement and HOV Program

Quarterly Project Report Update for Quarter Ending September 2008

Project Title & Location
SR 520 Bridge Replacement and HOV Project

Project Description
The overall program will replace the SR 520 corridor from I-5 to I-405 and reconfigure the existing HOV lanes east of I-405. This program is currently funded to complete environmental documentation and replace the Evergreen Point Bridge from Foster Island to Medina.

Contractor/Consultant
EIS – Parametrix, Public Involvement – EnviroIssues, General Engineering - HDR

Recent Progress
- Conducted contracting and environmental delivery workshops
- Public Open Houses to present the work of the mediation and the alternatives
- Continued in-depth 30% for the Floating Bridge and Eastside
- Began 30% design for the Westside
- Completed initial Westside Mediation and are continuing technical working sessions
- Begin work on Pontoon construction Environmental Impact Statement
- Continued negotiations for Eastside Right of Way parcels 
 

For more project information see the project web page at:

www.wsdot.wa.gov/projects/SR520bridge

Design Construction Impacts
The anticipated start of major construction is spring of 2010.  The project has received $52 million from the 2003 Nickel Package, $496 million from the 2005 Transportation Partnership Account, and $1,391 million of other State and Federal funds.  This money will be used for the completion of the Environmental Impact Statement, project design, right-of-way purchases and to begin construction.  Completion of project construction depends on additional funding from potential tolling, and other sources.

Environmental Impacts / Compliance
 A Draft EIS with a thorough analysis of the project alternatives and options was issued in August 2006.  Project has started work on a Supplemental Draft EIS incorporating the 4+2 lane configuration as identified by the Governor and legislators.  A Draft EIS for Pontoon Construction is now in development and is expected to be issued in the spring of 2009

Impacts to Traffic
Traffic impacts in the corridor have not yet been fully determined.  Pontoons for the new floating bridge will be constructed offsite and brought in through the Ballard Locks.  The new floating bridge will be built to the north of the existing bridge allowing traffic to continue use the exisiting bridge during construction.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering Fall 2003  Fall 2003 The fall of 2003 the SR 520 Bridge Replacement and HOV Project began design study in support of the corridor EIS.
Environmental Document (EIS Record of Decision) Complete Spring 2011   Draft EIS was issued in August 2006.  Supplemental Draft EIS is expected to be issued in late 2009.
Right of Way Certification Summer 2010   Certification of Right of Way on the Eastside
Advertisement Date Fall 2010 This date is for advertisement of the first major construction project in the SR 520 corridor. Offsite Construction of pontoons will begin sooner
Operationally Complete Fall of 2014 Completion of major construction in the corridor. New Floating Bridge is scheduled for opening in the fall of 2014
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $275 7%
Right-of-Way $190 5%
Construction $3,435 88%
Funded Project Costs $1,940 50%

Nickel funds included in above costs

52 1%

2005 Transportation Partnership Account

496 13%

  For more information, go to www.wsdot.wa.gov/projects

 Julie Meredith, WSDOT Project Director @ (206) 770-3568 or E-mail: MeredJL@wsdot.wa.gov