|
Project Title & Location
SR 520 Bridge Replacement and HOV Project
|
Project Description
The overall program will replace the SR 520 corridor from I-5 to I-405 and reconfigure the existing HOV lanes east of I-405. This program is currently funded to complete environmental documentation and replace the Evergreen Point Bridge from Foster Island to Medina.
|
|
Contractor/Consultant
EIS - Parametrix Public Involvement - EnviroIssues General Engineering - HDR
|
|
Recent Progress
1) Kicked off work with the Mediation team (Req. of ESSB 6099) 2) Kicked off work on the Finance, High Capacity Transit, and Health Assessment Plans (Req. of ESSB 6099) 3) WSDOT received Federal Urban Partnership Agreement Grant 4) Eastside Design Collaboration Team developing outreach plan 5) Completed draft cultural resources investigation reports on a potential Grays Harbor site for pontoon construction 6) Completed the placement 1.6 miles of quieter pavement for a 5-year evaluation period.
For more project information see the project web page at:
www.wsdot.wa.gov/projects/SR520bridge
|
|
Design Construction Impacts
The anticipated start of major construction is 2013. The project has received $52 million from the 2003 Nickel Package, $497 million from the 2005 Transportation Partnership Account, and $320 million of other State and Federal Bridge Replacement funds. This money will be used for the completion of the Environmental Impact Statement, project design, right-of-way purchases and to begin construction. Project construction depends on additional funding from potential tolling, a proposed regional transportation investment, and other sources.
|
|
Environmental Impacts / Compliance
A Draft EIS with a thorough analysis of the project alternatives and options was issued in August 2006. Project has started work on a Supplemental Draft EIS incorporating the 4+2 lane configuration as identified by the Governor and legislators.
|
Impacts to Traffic
Traffic impacts in the corridor have not yet been fully determined. Pontoons for the new floating bridge will be constructed offsite and brought in through the Ballard Locks. The new floating bridge will be built to the north of the existing bridge allowing traffic to continue use the exisiting bridge during construction.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Start Project Design
|
Spring 2006
|
Spring 2006
|
Spring of 2006 the project general engineering consultant team began the advancement of roadway and bridge design work. The design work on the project will continue through completion of plan preparation for construction contracts.
|
|
Issue Draft Environmental Impact Statement
|
August 2006
|
August 2006
|
Draft EIS was issued in August 2006 followed by a public comment period ending in October 2006.
|
|
Environmental document complete (Record of Decision)
|
Spring 2011
|
|
Development of a Supplemental Draft EIS is now underway.
|
|
Start Construction
|
Summer 2013
|
|
Project construction is partially funded by the 2005 Transportation Partnership Account. Additional revenue is needed to begin construction. At this time construction is scheduled to begin in the summer of 2013.
|
|
Operationally complete (Floating Bridge open to traffic)
|
Summer 2018
|
|
|