Recent Progress
1. All Draft Discipline Reports for the Draft EIS are now completed.
2. Completed the Pre-Draft EIS State and Lead Agency Review
3. Executive and Technical Committee Meetings, Jurisdictional Staff and Community briefings.
4. Continue to meet with Sound Transit and King County Metro to discuss opportunities for both projects to make better connections between SR520 and the Sound Transit Husky Stadium Station.
5. Held Design Options and High Level Bridge workshops and have begun screening of the options concepts.
6. Rescheduled the Draft EIS milestone to December 2005 to allow the Design Options Appendix to be made a part of the Draft EIS
Early Right of Way Phase:
1. Purchase of the selected UW parcel for Right of Way Acquisition has been deferred due to the uncertainty in future funding and the pressing need to begin advance design work. $4.0m is re-allocated to 05-07.
2. Record of Survey has been completed
3. New Right of Way Plan development is progressing.
To get cost and descriptions of project options see the project web page at: http://www.wsdot.wa.gov/projects/SR520bridge
|