Environmental and Design:
1. Draft EIS public comment period ended October 31st with over 1700 comments received
2. Project design team continuing work on the 10% design of the project alternatives
3. Completed preliminary geo-technical borings and Draft Engineering Report for geo-technical conditions
4. Completed Construction Phasing Scenarios
5. Continued planning for the development of a Special Project Construction Site that could accommodate the construction of the SR520 floating bridge pontoons. Conducted Expert Review workshop for pontoon construction methods
6. Developing a Quieter Pavement test project on SR520. Proposed construction in 2007.
Right of Way Acquisition:
Offer accepted for Right of Way on eastside parcel. Property is necessary for any alternative.
For more project information see the project web page at:
www.wsdot.wa.gov/projects/SR520bridge