SR 520 - Bridge Replacement and HOV Project

Quarterly Project Report Update for Quarter Ending December 2005

Project Title & Location
SR 520 Bridge Replacement and HOV Project

Project Description
The overall project will replace the SR 520 floating bridge and associated approaches. This project is currently funded to complete the environmental review, including an Environmental Impact Statement through the Record of Decision, early right-of-way acquisitions, and design.

Contractor/Consultant
EIS – Parametrix                                                Public Involvement - EnviroIssues

Recent Progress

Environmental and Design:

1. Amended Draft EIS to include jurisdictional/community sponsored design options including the Pacific Interchange, 108th Direct Access Ramps, Second Montlake Bridge, and Eastside Bike/Pedestrian alignment revisions.  The project team is continuing the environmental analysis on these options.  The milestone date for issuing the Draft EIS has been shifted to May 2006 to accommodate full analysis of the design options.

2. Enhancing corridor Catastrophic Failure Planning

3. Received interchange concepts from the Local Impact Committee.  These concepts have been evaluated and the project is now awaiting feedback from the City of Seattle.

4. Planning for the development of a site for the construction of the floating bridge pontoons.

5. Met with the Signatory Agency Committee (SAC) and the Muckleshoot Tribe to discuss the design options.  Feedback from these meetings was positive.

6. Other key activities include: Transit Service Planning, HCT Accommodation, public outreach regarding a possible bike/pedestrian connection to Madison Park, Section 106 (Cultural Resources) review, 3D scanning survey for design level mapping, 3D visualizations

 

Right of Way Acquisition:

Purchases of two selected R/W parcels in the Medina area are now being pursued.

 

For more project information see the project web page at:

www.wsdot.wa.gov/projects/SR520bridge

Design Construction Impacts

The anticipated start of major construction is mid-2009. The 2005 Cost Estimate Validation Process for the SR 520 project estimates the duration of construction to be seven to eight years and the total project cost to be in the range of $2.0 to $3.1 billion depending on the final alternative and options selected.  Options are being evaluated for replacement of the Evergreen Point Bridge as a first phase project.  The project has received $52 million from the 2003 Nickel Package and $500 million from the 2005 Transportation Partnership Account.  This money will be used for the completion of the Environmental Impact Statement, project design, right of way purchases and to begin construction.  Project construction depends on additional funding from tolling, a regional transportation investment, and other sources.

Environmental Impacts / Compliance

A Draft Environmental Impact Statement with a complete analysis of the project alternatives and design options is scheduled to be issued in May 2006 followed by a public comment period during the summer.  The goal for the project will be to select a preferred alternative by the end of the summer once all public comments have been evaluated.

Impacts to Traffic
Traffic impacts in the corridor have not yet been fully determined.  Pontoons for the new floating bridge will be constructed offsite and brought in through the Ballard Locks.  The new floating bridge will be built to the north of the existing bridge allowing traffic to continue use the exisiting bridge during construction.

Project Milestones Scheduled Attained Milestone Outlook
Start Right of Way Acquisition Spring 2004  Ongoing Purchase of two selected R/W parcels in the Medina area are now being pursued.
Start Environmental Permitting Process Summer 2005  Ongoing Permitting discussions are continuing with resource agencies.  No permits have been applied for or issued at this time.
Start Project Design Spring 2006   Start of detailed project design is scheduled to begin in spring of 2006 and will continue through completion of the design phase of the project.
Issue Draft Environmental Impact Statement May 2006

Draft EIS is scheduled to be issued in May 2006 followed by a public comment period during the summer.

Start Construction Summer 2009 Project construction is partially funded by the 2005 Transportation Partnership Account.  Additional revenue is needed to begin construction.  At this time construction is scheduled to being in the summer of 2009.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 167.4 29%
Right-of-Way 17 3%
Construction 390 68%
Funded Project Costs 574.4 100.0%

Nickel funds included in above costs

52.3 9%

2005 Transportation Partnership Account

500 87%

  For more information, go to www.wsdot.wa.gov/projects

Julie Meredith, WSDOT Engineering Manager @ (206) 381-6406 or E-mail: MeredJL@wsdot.wa.gov