June 2009
The operator of the CW Branch (Cheney to Coulee City) encountered financial problems in late 2008 and early 2009 that threatened final termination of the contract. With assistance from the PCC Rail Authority, the State and EWG negotiated benchmarks that EWG must meet on an ongoing basis in order to operate beyond December 31, 2009. If EWG continues to meet them as they have been doing, the original agreement will control operations again on January 1, 2010.
The Legislature appropriated $3.6 million for projects on the PCC Rail System that are urgently needed. Construction began in early August 2008. The project on the P&L Branch was completed on November 20, 2008. Completion of the projects for the other two branches was delayed until spring because of winter weather. The projects were completed in May 2009.
The Legislature also appropriated $8.6 million to WSDOT to grant to the PCC Rail Authority for further rehabilitation on the PCC. The grant was made, and the PCC Rail Authority requested that WSDOT administer the funds and projects based on information collected in 2007. A project is being developed for each of the three lines. The P & L Branch project went to ad on May 20th. The project for the CW Branch went to ad on June 3rd, and the project for the PV Hooper Branch will go to ad on June 10th.