I-5 - NB MLK Jr Way to NE Ravenna Br - Pavement Repair & More

Project news

  • Last update: Monday, Oct. 15
  • Major weekend-long lane reductions on northbound I-5 are complete for 2018.
  • Drivers should expect lane closures nightly Sunday through Thursday between 8 p.m. and 5 a.m.
  • Sign up to receive email updates about this project and other King County topics.

Overview

Contractor crews working on nearly 13 miles of northbound Interstate 5 from Martin Luther King Junior Way South/State Route 900 to Northeast Ravenna Boulevard will:

  • replace 37 expansion joints 
  • replace large sections of concrete pavement
  • grind the roadway 
  • repave
  • add pedestrian ramp upgrades and safety barrier improvements. 

This is substantial weather-sensitive highway work that will require multiple nighttime lane closures, along with weekend-long lane reductions during the busy summer travel months. The project schedule must be carefully coordinated with nearby construction projects, the City of Seattle and transit agencies.

Why is WSDOT repairing this section of northbound I-5?
Approximately 100,000 vehicles use this section of northbound I-5 each day. The interstate was built in the 1960s. The concrete pavement was only intended to last 25 years, but has now doubled its lifespan.

In addition to its age, the increasing number of cars and heavy trucks on the road, along with freeze/thaw cycles, have contributed to the deterioration of the highway. Drivers can notice this in the tell-tale "thump, thump, thump" of their vehicle's wheels. That's the sign of a broken concrete panel that is rocking back and forth, and beyond its lifespan.

What should drivers expect?
To successfully complete the work, the following northbound I-5 traffic control is required:

  • Multiple weekend-long lane reductions and associated ramp closures.
  • Overnight lane and ramp closures throughout the duration of the project.
  • Generally, no closures will be allowed on Friday nights, except during the weekend lane reductions.

Work schedule:
Most work on this project is taking place during overnight lane reductions. However, so far we have scheduled the following weekend-long lane or full closures:

  • April 20-23: Two lanes open (Completed)
  • May 11-14: Two lanes open (Completed)
  • May 18-21: Two lanes open (Completed)
  • June 1-4: Full northbound I-5 closure (Completed)
  • July 13-16: Full northbound I-5 closure (Completed)
  • August 10-13: Two lanes open (Completed)
  • Oct. 12-15: Two lanes open (Completed)

The End Result
This preservation and improvement work will extend the useful life of the interstate for years to come, creating safer and improved driving conditions for the thousands of travelers who use it each day. This project is part of a years-long effort to preserve I-5 through King County.

Needs & benefits

  • Preservation: Replacing broken concrete panels, repaving, and grinding the roadway improves the driving surface and extends the life of I-5. Replacing bridge expansion joints ensures the highway will remain safe and operational.
  • Safety: Improving the highway surface eliminates and helps prevent future potholes, cracks and wheel ruts, making for a smoother ride for drivers. Replacing expansion joints reduces the chances that an aging expansion joint could become dislodged or fail, creating a hazard to drivers and forcing an emergency closure of the bridge. Reconstructed ADA-compliant pedestrian ramps create an easier transition between street and sidewalk.
  • Economic: Replacing broken concrete panels, repaving and replacing bridge expansion joints reduces the need for emergency repairs, which are costly to taxpayers and can cause additional congestion during peak commute hours.

Timeline

  • December 2016: Project was advertised for competitive bidding.
  • May 2017: Project was awarded to Guy F. Atkinson Construction, LLC.
  • August 2017: Construction is scheduled to begin.
  • Late 2019: Construction is scheduled to be complete.

Funding

Financial Data for PIN 100512T, 100515B, 100515C, 100516E, 100516G, 100519B, 100522C
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $16,252
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $34,306
CWA $0
Total $50,556

Contact

Diana Barreto
Communications
206-462-6354
barretd@consultant.wsdot.wa.gov

A small map of the pavement repair project along nearly 13 miles of northbound I-5 from Martin Luther King Junior Way South/SR 900 to Northeast Ravenna Boulevard in Seattle.

A small photo of several cracked and patched concrete panels and deteriorated expansion joints on nothbound I-5 through Seattle.

There are numerous cracked and patched concrete panels and failing bridge expansion joints on northbound I-5 through Seattle.