Skip Top Navigation

Ready for Bertha: SR 99 tunnel’s launch pit complete

Get Our Mobile App

  • Our Android and iPhone apps include statewide traffic cameras, travel alerts, mountain pass reports, ferry schedules and alerts, northbound Canadian border wait times and more.

Date:  Tuesday, May 14, 2013

Contact: KaDeena Yerkan, Alaskan Way Viaduct Replacement Program,206-805-2846, (cell) 206-795-1876 (Seattle)

Chad Schuster, Alaskan Way Viaduct Replacement Program, 206-805-2869

Tunneling machine assembly continues, Bertha on track for summer launch

SEATTLE – Last spring, a field of unturned dirt marked the spot where Bertha will begin digging the two-mile State Route 99 tunnel beneath downtown Seattle. One year and 86,000 cubic yards of soil later, it’s a pit fit for the world’s largest tunneling machine.

Crews finished building Bertha’s 80-foot-deep launch pit on Sunday after nearly a year spent building its underground walls, removing soil and building the infrastructure needed to support the nearly 7,000-ton machine. Its completion clears the way for tunneling to start this summer, once Bertha’s 41 pieces have been reassembled and tested at the bottom of the pit.

“If Bertha is the star of the project, the launch pit is her stage,” said Linea Laird, Washington State Department of Transportation administrator for the Alaskan Way Viaduct Replacement Program. “Completing the launch pit means we’re that much closer to the start of tunneling.”

Launch-pit construction started last summer in the work zone west of Seattle’s stadiums. Before excavation began, crews drilled more than 200 piles as many as 100 feet into the ground to form the pit’s walls. The perimeter of the pit is 80 feet wide and 400 feet long.

Assembly of the machine started at the south end of the pit shortly after it arrived last month from Osaka, Japan. Now that the front end of the pit is complete, crews have started building the body of the machine near the spot where it will first push into Seattle’s soil.

Bertha, for whom WSDOT launched a Twitter account in December, said she was thrilled with the way the pit turned out. “I can’t imagine anything fitting me as well as this launch pit,” @BerthaDigsSR99 tweeted Tuesday. “I now know exactly how the people in mattress commercials feel.”

Crews are also preparing the surrounding area for tunneling, including strengthening the soil and building protected work areas along the initial section of the tunnel route so they can perform scheduled inspections of the machine before it begins digging beneath downtown. Meanwhile, work continues near the north end of the Battery Street Tunnel to prepare the area where Bertha will emerge at the end of tunneling.

A 10-foot-long interactive model of Bertha is on display at Milepost 31, the project’s information center in Pioneer Square. Photos of the machine and construction in Seattle are also available.

For more information about the SR 99 Tunnel Project, visit http://www.alaskanwayviaduct.org/.


< Go Back