3 fish-friendly culverts installed, 1 bridge demolished during weekend work

Get Our Mobile App

  • Our Android and iPhone apps include statewide traffic cameras, travel alerts, mountain pass reports, ferry schedules and alerts, northbound Canadian border wait times and more.

Date:  Monday, August 13, 2012

Contact: Jamie Holter, WSDOT traffic communications, 206-440-4698
Ryan Bianchi, WSDOT SR 520 communications, 206-819-7230
Steve Peer, WSDOT SR 167 communications, 425-301-2023

SEATTLE – Crews reopened State Route 520 and State Route 167 on time this morning after separate weekend-long closures. All lanes of SR 520 and SR 167 opened by 4:30 a.m., just in time for the morning commute.

Good weather and highly coordinated plans helped crews get the work done on time. During the weekend closures, crews installed culverts in Bellevue and Renton and knocked down a highway overpass in Bellevue. Add in work on State Route 9 in Clearview and Lake Stevens and it was the largest construction weekend of the year for the Washington State Department of Transportation.

“I want to thank drivers for their patience this weekend as we completed this essential work.” said Lorena Eng, WSDOT regional administrator. “Although we had some congestion on Saturday before the Seahawks game, most of the traffic backups were minimal thanks to people altering their travel plans and routes.”

SR 520 work
On SR 520, crews demolished the old Bellevue Way Northeast overpass to make room for a new, wider overpass, and installed a fish-friendly culvert just east of Bellevue Way Northeast. The overpass demolition resulted in 650 cubic yards of concrete rubble and more than 92,000 pounds of rebar that will be recycled.

To install the fish-friendly culvert, crews dug a 25-foot-deep trench across all lanes of the highway, inserted precast concrete culvert sections, then repaved the highway. When complete, the culvert will be more than 230 feet long.

SR 167 work
On SR 167, crews installed a 220-foot-long culvert just south of Interstate 405 in Renton. That work required crews to dig a 25-foot-deep trench across all lanes of the highway, then remove and replace about 100 feet of embankment and roadway surface.

SR 9 work
On SR 9 in Clearview, crews replaced a 24-inch-diameter culvert with an 84-inch-diameter culvert to improve fish passage under the highway. Crews also widened the intersection of SR 92 and SR 9 in Lake Stevens.

Thanks to drivers who paid attention to traffic conditions and adjusted their plans this weekend, delays were limited to typically congested areas such as Interstate 90 between Bellevue and Seattle during peak drive times. Northbound SR 167 saw some daytime delays, starting in Kent.

Hyperlinks within the news release

• SR 167 closure: www.wsdot.wa.gov/Projects/I405/Sr167PantherCreek.htm
• SR 520 closure:www.wsdot.wa.gov/Projects/SR520Bridge/MedinaTo202/default.htm
• SR 9 Clearview: www.wsdot.wa.gov/projects/sr9/212thse_176thse/
• SR 9/SR 92: http://www.wsdot.wa.gov/Projects/SR9/SR92intersection/default.htm